UPS SYSTEM INSTALLATION
EATON
Powerware
®
9395 UPS (650–825 kVA) Installation and Operation Manual
S
164201725 Rev 2
www.powerware.com
4−2
NOTE
For the following steps, verify that the forklift or pallet jack is rated to handle the weight of the
cabinet (see Table 3-1 on page 3−2 for cabinet weight).
1.
If not already accomplished, use a forklift or pallet jack to move the ISBM and
UPM sections to the installation area, or as close as possible, before unloading
from the pallets. If possible, move each section using the pallet. Insert the forklift
or pallet jack forks from the right side of the pallet (facing the cabinet), between
the supports on the bottom of the pallet (see Figure 3-8 and Figure 3-9 on
page 3−6 for the ISBM and UPM section center of gravity measurements). If the
sections must be moved using the cabinet front or rear fork lift slots, see the
caution statements at the beginning of this procedure.
2.
Remove the three bolts securing the left side shipping bracket to the cabinet and
three bolts securing the bracket to the pallet (see Figure 4-1 or Figure 4-3).
Remove the left side shipping bracket.
3.
Remove the three bolts securing the right side shipping bracket to the cabinet
and three bolts securing the bracket to the pallet (see Figure 4-2 or Figure 4-4).
Remove the right side shipping bracket.
Shipping Bracket
Bolts
Shipping Bracket
Bolts
Pallet
Left Side Shipping
Bracket
Front Door
Figure 4-1. Removing the ISBM Section Left Side Shipping Bracket