Enervex MFD – Horizontal Termination Installation
1.
Before installing the MFD on the chimney, a power cable should be wired to the actuator and the actuator
cover should be secured (
Figure 30)
.
2.
Use 4-conductor cable (min. 18 AWG) with a weatherproof jacket such as rubber or silicone. Install a
weatherproof cable connector on the side of the actuator cover to prevent water ingress to the actuator.
3.
Use (6) of the included sheet metal screws to secure the actuator cover to the MFD. Once secure, apply a
bead of silicone around the seams of the cover.
4.
Mount the MFD outdoors at the end of a steel chimney. Slide the collar of the MFD into the steel chimney
until the damper rests on the stop flange. Sheet metal screws may be installed around the collar into the
chimney for additional support.
Fasten the MFD to noncombustible framing with metal fasteners or bolts with
locking nuts (
Figure 31
)
NOTE:
An 18” clearance to combustible is required for the MFD.
FIGURE 30
FIGURE 31
13”