6.0 METER INSTALLATION

6.1 Mounting the Class 3400 Meter

Use appropriately sized mounting hardware to fasten the meter enclosure to the 
selected mounting surface. The four housing mounting holes are centered 8.75” H x 4” 
W for the CL3400.

NOTE: Meters supplied in plastic NEMA 4X enclosures and NEMA JIC Steel 

Enclosures (UL Type 1) enclosures must be installed indoors.

6.2 Main Power Board Connections

1.

Installing a temporary ground for ESD protection: 

With all circuits de-energized, connect a temporary protective earth ground con-

nection for ESD protection. Prior to performing any unit wiring, be sure to dis-

charge any static on your person.

2.

Installing the Class 3400 protective earth ground: 

Connect an earth ground wire to the Class 3400 protective earth ground lug with 

a torque of 7 N-m.

M34684

6-35/64 (166)

6-35/64

(166)

5/8 (16)

7-51/64

(198)

3-17/64 (83)

1-5/8

(41)

3-25/64

(86)

Ø 1-3/32 (28) THROUGH

NEAR SIDE ONLY 

Summary of Contents for Class 3400 Meter

Page 1: ...62 0391 03 INSTALLATION INSTRUCTIONS Class 3400 Meter ADVANCED KWH DEMAND METER WITH COMMUNICATIONS E Mon 1985 Douglas Drive North Golden Valley MN 55422 www emon com info emon com...

Page 2: ...ed with your products we provide toll free technical and sales support Monday through Friday 8 00 am to 7 30 pm EST 800 334 3666 You may also reach us via email at info emon com If you have questions...

Page 3: ...16 Section 6 6 Line Voltage Current Sensor Diagnostics 16 Section 6 7 RS 485 Wiring 18 Section 6 8 RS 232 Communications 19 Section 6 9 Modem Wiring 22 Section 6 10 Modbus RTU Wiring 25 Section 6 11 B...

Page 4: ...proper installation of this meter Verify the input voltage rating and configuration on the unit panel label to ensure that it is suitable for the intended electrical service 3400 meters labeled for 12...

Page 5: ...or The protection and safety features provided by this equipment may become impaired or otherwise compromised NOTE If any trouble arises during installation or functional verification opera tions do n...

Page 6: ...is connected to the correct terminals One three terminal screw connector RS485 is for RS 485 communications One two terminal screw connection output is for a pulse output One RJ 45 jack J8 is provide...

Page 7: ...nd the board mounts on the inside of the housing door No additional connections to the display board are required The display board s LCD readout indicates the metered values as well as errors associa...

Page 8: ...Type kit split core scs solid core non supplied blank Brand Class Voltage Amperage Enclosure Communication Protocol Current Sensor Option Current Sensor Option Current Sensor Option Example E 34 208...

Page 9: ...Pollution Degree Degree 2 In Accordance With IEC 664 Installation Overvoltage Category Category III Measurement Category Category III Enclosure Material UL Type 1 JIC Steel or Type 4X Plastic Rain Tig...

Page 10: ...ed CAT 5e cable 8 conductor stranded 24 AWG Cable Connector RJ 45 termination protocol 10 100 base T Cable Distance 450 feet Load Control Contacts Contact Closure Set by user Contact Rating 28Vdc 10A...

Page 11: ...io or television reception which can be determined by turning the equipment off and on the user is encouraged to try to correct the interference by one or more of the following measures Reorient or re...

Page 12: ...hock exists Prior to performing any wiring operations review all contents of the user manual and de energize the MAINS power switch Only qualified personnel should perform installation wiring Installa...

Page 13: ...s must be installed indoors 6 2 Main Power Board Connections 1 Installing a temporary ground for ESD protection With all circuits de energized connect a temporary protective earth ground con nection f...

Page 14: ...ing of the enclosure 4 Unit MAINS Wiring The first four positions of terminal block TB1 located at the bottom left corner of the main power board are clearly labeled Phase A B C N neutral Earth Ground...

Page 15: ...ach of their respective terminal block positions and tightened down verify that each terminal block screw is securely fas tened by gently tugging on each conductor NOTE On Single phase order SP option...

Page 16: ...Repeat Step F Once the meter displays the correct line voltages and there are no error messages you are ready to connect the current sensors to the meter Before continuing with the installation verify...

Page 17: ...CLASS 3400 METER 17 62 0391 03 NOTE The meter will be reset later via the software during startup proce dures...

Page 18: ...3400 meters are supplied with this sensor type 2 Solid core current sensor This sensor does not open and requires the monitored conductor to be removed from the circuit to install the current sensor T...

Page 19: ...sor connects to two terminals one labeled Black and the other White Current sensors should be connected to the meter one at a time and verified using the current sensor diagnostic program Connect one...

Page 20: ...2 AWG SENSOR CONNECTIONS W WHITE LEAD B BLACK LEAD NEUTRAL NOT USED IN DELTA SYSTEM LITTLEFUSE PART NUMBER KLDR 100 1 10A 600 VAC INLINE FUSE PER CONDUCTOR LITTLEFUSE PART NUMBER KLDR 100 1 1 1 1 LINE...

Reviews: