background image

4

Dutchwest

30003847

Installation

SAFETY NOTICE:  IF YOUR DUTCHWEST CON-
VECTION HEATER IS NOT PROPERLY INSTALLED, 
OPERATED AND MAINTAINED, A HOUSE FIRE MAY 
RESULT.  FOR SAFETY, FOLLOW ALL INSTALLA-
TION, OPERATION AND MAINTENANCE DIREC-
TIONS.  CONTACT LOCAL BUILDING OFFICIALS 
ABOUT RESTRICTIONS AND INSTALLATION 
INSPECTION REQUIREMENTS IN YOUR AREA.

Before you begin the installation, review your plans to 
confirm that:

  Your stove and chimney connector will be far enough 

from combustible material to meet all clearance 
requirements.

  The floor protector is large enough and is construct-

ed properly to meet all requirements.

  You have obtained all necessary permits from local 

authorities.

Your local building official is the final authority for ap-
proving your installation as safe and for determining 
that it meets local and state codes.
Clearance and installation information is printed on the 
metal label attached to the rear of the stove.  Local au-
thorities generally will accept the label as evidence that, 
when the stove is installed according to the information 
on the label and in this manual, the installation meets 
codes and can be approved.
Codes vary in different countries, however.  Before 
starting the installation, review your plans with the local 
building authority.  Your local dealer can provide any 
additional information needed.

Important:

  

Failure to follow these installation 

instructions may result in a dangerous situation, in-
cluding a chimney or house fire.  Follow all instruc-
tions exactly, and do not allow makeshift compro-
mises to endanger property and personal safety

.

All local regulations, including those referring to 
national and European standards need to be com-
plied with when installing this stove.

Chimney Types

Your Dutchwest Convection Heater must be connected 
to a sound masonry chimney that meets local codes, a 
relined masonry chimney that meets local codes, or to 
an approved prefabricated metal chimney.  Whatever 
kind you use, the chimney and chimney connector must 
be in good condition and kept clean.

Masonry Chimneys

If you use an existing masonry chimney, it must be 
inspected to ensure safe condition before the stove 
is installed.  Your local professional chimney sweep, 
building inspector, or fire department official will be able 
either to make the inspection or to direct you to some-
one who can. 
The flue and chimney design must meet requirement 
J2, Part J of the building regulations 2000 (Combustion 
Appliances and Fuel Storage Systems).
An inspection of the chimney must confirm that it has 
a lining. Do not use an unlined chimney.  The chimney 
should also be examined for cracks, loose mortar, other 
signs of deterioration, and blockage.  Repair any de-
fects before the chimney is used with your stove.  
Unused openings in an existing masonry chimney must 
be sealed with masonry to the thickness of the chimney 
wall, and the chimney liner should be repaired.  Open-
ings sealed with pie plates or wallpaper are a hazard 
and should be sealed with mortar or refractory cement.  
In the event of a chimney fire, flames and smoke may 
be forced out of these unused thimbles.
The chimney should be thoroughly cleaned before use.
A newly-built masonry chimney must conform to the 
standards of your local building code or, in the absence 
of a local code, to a recognized national code. Masonry 
chimneys must be lined, either with code-approved 
masonry or pre-cast refractory tiles, stainless steel 
pipe, or a code-approved, “poured-in-place” liner.  The 
chimney’s clean-out door must seal tightly.

ST241

chimney types

12/13/99   djt

Prefabricated Double-Wall 

Insulated Chimney

Tile Lined 

Masonry 

Chimney

ST241

Fig. 2

  If in sound condition and approved for use, either a 

masonry or a prefabricated chimney may be used.

Summary of Contents for 2460CE

Page 1: ...HIS MANUAL Retain for future use If this heater is not properly installed operated and maintained a house re may result For safety follow all installation operation and maintenance directions Contact...

Page 2: ...tates and EN13240 2001 A2 2004 for Europe Dutchwest models are not listed for mobile home installations Patents U S D288357 4502395 4646712 Canada 1235969 Other foreign mechanical patents issued Acces...

Page 3: ...sq ft 1 112 224 sq m 1200 2400 sq ft 1 Fuel Size type 480 mm 19 wood 560 mm 22 wood 640 mm 25 wood Flue mass gas ow 5 7 g s 7 1 g s 8 4 g s CO emissions 13 O2 1700 ppm 2300 ppm 2300 pmm Weight 172 kg...

Page 4: ...n Heater must be connected to a sound masonry chimney that meets local codes a relined masonry chimney that meets local codes or to an approved prefabricated metal chimney Whatever kind you use the ch...

Page 5: ...ego ries a Vitreous enamelled steel pipe complying with BS 6999 1989 1996 b Pipes made from stainless steel as descirbed in BS EN 1008 1 1995 grades 1 4401 1 4404 1 4432 or 1 4436 with ue wall thickne...

Page 6: ...s with at least three sheet metal screws 3 Secure the chimney connector to the chimney In structions for various installations follow below 4 Con rm that the installed stove and chimney con nector are...

Page 7: ...chimney The liner of the replace chimney should extend at least to the point at which the chimney connector enters the chimney Follow all the guidelines for installing a chimney connector into a free...

Page 8: ...e design your installation so the con nector does not pass through a combustible wall If you must use a wall pass through in your installation check with your building inspector before you begin and c...

Page 9: ...The oor protector must also meet standard requirements for freestanding installations Floor Protection for Fireplace Installations with Standard Legs Fireplace installations with the standard legs an...

Page 10: ...ecommended rear clearance to noncom bustible surfaces 50 mm 2 NOTE The minimum thickness of solid noncombus tible materials is speci ed in section 2 of Document J in relation to the clearance of the a...

Page 11: ...l e a s t 3 x D at least 1 5 x D at least 1 5 x D Plan Without Shield Plan With Shield Air space of at least 12 mm between noncombustible shield and combustible material Fluepipe at least 1 5 x D at...

Page 12: ...quired in many instal lations Refer to the oor protection information found in the Installation Section of this manual Attach the Legs and Heat Shield Place the stove on its back on a soft surface suc...

Page 13: ...e lever points straight down Fig 18 The secondary air inlet over the side door admits air to the catalytic combustor only for high ef ciency at high combustor temperatures Use a gloved hand or the met...

Page 14: ...designed to burn natural wood only Do not burn other fuels Never burn pressure treated wood painted or stained wood or glossy newsprint High ef ciencies and low emissions are possible when burning ai...

Page 15: ...courage creosote formation in the stovepipe and chimney higher temperatures can cause stove parts to burn out prematurely Always operate the stove accord ing to rebox temperatures Besides the air cont...

Page 16: ...ld be well established within 10 15 minutes You may gradually build it up by adding a few sticks at a time of a progressively larger size Continue to build the re until a live coal bed begins to form...

Page 17: ...d back of the ash pan Empty the ash drawer regularly typically every one to three days The frequency will vary depending on how hot you run your stove the hotter the re the more wood you burn and the...

Page 18: ...specially made for this pur pose Dry the glass completely Adjust the Door Latch The door latches must close tightly to ensure a good seal between the each door and the stove plates With time and use t...

Page 19: ...up Use a 11 mm 7 16 socket wrench with socket extension to adjust the linkage 1 In an alternating pattern rst loosen and then re move the four bolts that secure the top plate to the sides of the stov...

Page 20: ...od plan on how to handle one Inspect Regularly Clean As Required Inspect the chimney and chimney connector twice monthly and clean if necessary Let the stove cool completely before you inspect the chi...

Page 21: ...r should be inspected annually for a build up of y ash and cleaned if necessary This may be done during examination of the catalytic combustor When to Suspect A Combustor Problem There are two ways to...

Page 22: ...all it Be sure rst to carefully wrap a new Interam gasket an extra was provided with your stove around its perimeter before replacement Insert the gasketed combustor gently back into position and repl...

Page 23: ...ces for creosote and y ash to deposit It is important to follow the operating instructions in order to minimize these deposits and to periodically inspect your catalyst for signs of blockage Masking a...

Page 24: ...akes the steel chimney support a good draft more quickly than masonry does Steel chimneys are not as attractive as masonry but they are very durable and generally outperform masonry Indoor Outdoor Loc...

Page 25: ...p within the rebox until reaching a density and temperature at which they ignite With this ignition you may hear a muf ed pop ping sound and see a bit of smoke forced out of the stove This condition i...

Page 26: ...changes in design materials speci cations prices and discontinue colors and products at any time without notice Dutchwest Convection Heater Models 2460CE 2461CE 2462CE Item Description 2460CE 2461CE...

Page 27: ...Collar 7000969 7000969 1304280 35 Leg 7000016 7000016 7000016 36 Damper Handle Stub 5004265 5004265 5004265 37 Ash Door Handle 5004237 5004237 5004237 38 Ash Pan 7000G79 7000G69 7000G89 39 Gasket for...

Page 28: ...28 Dutchwest 30003847...

Page 29: ...29 Dutchwest 30003847...

Page 30: ...30 Dutchwest 30003847...

Page 31: ...lusions Limitations 1 This product must be installed or serviced by a quali ed installer preferably NFI or WETT Canada certi ed as prescribed by the local jurisdiction It must be installed and operate...

Page 32: ...MHSC 149 Cleveland Drive Paris Kentucky 40361 www mhsc com...