User Manual
45
First commissioning
Pay attention to release the emergency stop switch
Arc-LED and cyclo-LED is blue
The nameplate is located to the left of the charger
You can start charge with plug in charging gun or use APP
the power supply has been established when arc-LED blink and cyclo-LED often on
Before the first commissioning the
According to “Ordinance on general conditions for grid connection and its use for electricity
supply in Low voltage (Low Voltage Connection Ordinance - NAV)“ in
§
19 the following
points have to be clarified with the network operator:
„
Section 19 Operation of electrical systems, consumables and charging devices, own systems
(1) The system and consumables are to be operated by the connectee or user in such a way
that faults occur other connectees or users and disruptive repercussions on network
operator facilities or Third parties are e
x
cluded.
(2) E
x
tensions and changes to systems as well as the use of additional consumer devices are
the
Notify network operators if this increases the capacity to be maintained or with network
repercussions is to be e
x
pected. Charging devices for electric vehicles are also prior to
commissioning to communicate. Their commissioning also requires the prior consent of the
network operator, if their total rated power e
x
ceeds 12 kilovoltampere per electrical system
;
is the network operator in this case, obliged to e
x
press itself within two months of receiving
the notification. Is that true Network operator, he has the impediment, possible remedial
measures of the network operator and the Connected party or user and a time required for
this by the network operator. The network operator can regulate details of the content and
form of the messages.
(3) The connectee or user must notify the network operator before setting up his own system
do. The connectee or user must take appropriate measures to ensure that his Own plant no
harmful repercussions in the electricity supply network are possible. The connection of own
systems is to be coordinated with the network operator. This can be the connection of
compliance with the make it dependent on measures to be taken to protect against reverse
voltage in accordance with Section 20.“