   1.  The furnace must be located on a noncombustible floor

   2.  For greenhouse installation it is recommended to locate furnace on the naturally coldest end of green-

house. (north or west) If greenhouse is sloped, place furnace at lowest end of greenhouse. Installing an air tun-

nel with a fan is the optimal way to circulate air. Any horizontal or ceiling fans will help. When fans are not an

option try installing 2 pieces of tin on top of furnace. Start up 16” from back top edge of furnace and run 16' of

tin, 2 pieces wide, up into the peak of the greenhouse. This will help start your natural circulation. 

See drawing below.

   3.  For building installation. It is recommended that the furnace be centrally located in the building in such a

way that air can naturally circulate around furnace and around the whole building. If this is not and option it is

recommended to install fans to circulate the air. See drawing on page 5.

   4.  You must follow all clearance to combustibles.

   5.  Connection of the furnace to the chimney should

be made as directly as possible (6 feet maximum hori-

zontal) and not more than two bends, when needed,

should be used. No reduction in flue pipe below 10

inches in diameter should be used. The single wall

chimney connector connecting the furnace to the chim-

ney should be at least 24 gauge. Thicker gauges are

available and will resist corrosion longer and need

fewer replacements. Slope the flue pipe back towards

the furnace, 1/4” per foot of horizontal run. That way if

any condensation forms in the pipe it will be carried

back into the furnace. The connector pipe should be in-

stalled so that the upper pipe section fits inside the

lower section. This way any condensation building up

inside the pipe will stay inside the pipe as it flows down

the inside surface. Horizontal pipe runs should have

the pipe seams turned up. Particular attention should

be paid to the point where the flue passes through a

wall or ceiling. This penetration should always be

made with a thimble, insulated pipe, and then proper

accessories following manufacturers instructions.

Chimney connectors must not pass through the ceiling,

concealed spaces, or enter the chimney in the attic,

unless proper clearance or insulated pipe is used following manufacturers

instructions. 

REMEMBER

that all single wall chimney connectors  should be connected with at least 3 sheet

metal screws per joint. A fire in the stack may cause vibration and poorly fastened single wall chimney connec-

tors may come apart causing an extreme fire and smoke hazard. Do not extend single wall chimney connector

past the inside edge of the flue liner. If you have a manufactured Stainless Steel chimney, attach single wall

chimney connectors to single wall chimney connector adapter. Where the single wall chimney connector con-

nects to a masonry chimney, the flu to the chimney should be larger than the stove single wall chimney connec-

tor so you can insert the single wall chimney connector out to the inside edge of the chimney, but not past.

Locating Furnace

When possible, locate furnace on north or west end of greenhouse.

Above drawing shown with outside fire door.

Optional 2 pieces of tin, 6’ wide x 16’ long at an angle above furnace

to enhance natural circulation.

36” minimum

height above peak

10” Exhaust

4

Summary of Contents for Greenhouse Blast GH450

Page 1: ...ce you must Read all instructions carefully Install smoke and carbon monoxide detectors MADE IN USA By D S MACHINE SHOP Do Not Discard This Manual DS Greenhouse Blast High Efficiency Wood or Coal Green House Furnace Model GH450 OWNER S MANUAL ...

Page 2: ... Operational Work Practice Standards 1 When burning wood burn only seasoned dry cord wood that has been dried then warmed before firing Warming cord wood means placing in a heated building for 1 day before burning 2 Keep wood under cover in a wood shed or a tarp 3 Right after delivery stack cord wood under cover 4 Split cord wood before drying 5 Do not burn green wood it needs to have no more than...

Page 3: ...smell an odor This is normal during the first operation You may want to assemble the furnace out of doors and build a small fire in it to BURN OFF this dirt and oil before installing unit Starting A Wood Fire When starting a wood fire use the same steps as starting a coal fire above but do not add coal Allow ash to build up on top of grates this will not choke fire until it covers louvers For most...

Page 4: ... back into the furnace The connector pipe should be in stalled so that the upper pipe section fits inside the lower section This way any condensation building up inside the pipe will stay inside the pipe as it flows down the inside surface Horizontal pipe runs should have the pipe seams turned up Particular attention should be paid to the point where the flue passes through a wall or ceiling This ...

Page 5: ...minimum height of a chimney system for the D S Furnace is 20 feet The chimney must exceed the roof of a house at a minimum of 3 feet at any point of exit In a pitched roof installation the chimney must be 2 feet higher than anything within a 10 foot radius of the chimney It is important to have a chimney draft of 0 06 water column It is required to abide by the manufac turer s instructions on Clas...

Page 6: ...Thermostat Hook Up for GH Blast 6 ...

Page 7: ...n on thermostat Then from out of thermostat to cylinder at furnace as per diagram Air regulator needs to be set at 20psi D Test the unit after installed to make sure draft lid opens and closes properly Then build your fire in furnace and set thermostat to desired temperature DS Pneumatic Powered Thermostat Kit I I I I I I I I I I I I I II Air Regulator set at 20psi Thermostat Mount Cylinder on sid...

Page 8: ...ING Top vent door must be OPEN when O F D is closed to allow air circulation around front of furnace O F D Flange O F D Flange OPEN CLOSE INSTALLATION INSTRUCTIONS Install O F D on GH 450 Furnace See drawing above Install the GH 450 Furnace with the O F D already installed into the wall of your greenhouse With the GH 450 Furnace and Optional O F D in final position frame wall of greenhouse to with...

Page 9: ...ck 10 2 1 2 x 4 1 2 x 9 Back 2 2 1 2 x 2 1 4 x 9 Right Side 22 2 1 2 x 4 1 2 x 9 Right Side 2 2 1 2 x 1 3 4 x 9 Left Side 22 2 1 2 x 4 1 2 x 9 Left Side 2 2 1 2 x 1 3 4 x 9 TOTAL 58 2 1 2 x 4 1 2 x 9 3 2 1 2 x 2 1 4 x 9 4 2 1 2 x 1 3 4 x 9 ALL Fire Brick are 2 1 2 x 4 1 2 x 9 unless noted otherwise 2 1 2 x 2 1 4 x 9 2 1 2 x 1 3 4 x 9 2 1 2 x 2 1 4 x 9 2 1 2 x 1 3 4 x 9 9 Cast Iron Louvers Cast Iro...

Page 10: ...8 Fire Door 450 18 FD 2 Cast Iron Ash Door 450 ASH6 D 2 Spinners on Fire Door 450 4 SPOB 2 1 2 Spring Handle on Ash Doors 450 12 CSH 1 5 8 Spring Handle on Fire Door 450 58 CSH 1 Ash Pan 15 1 2 w x 26 d x 6 h 450 155 26 6AP 1 Ash Pan 15 1 2 w x 28 d x 6 h 450 155 28 6AP 1 Back Ash Shaker Bar Assembly 450 160 BASBA 1 Front Ash Shaker Bar Assembly 450 160 FASBA 4 Cast Iron Louvers 450 CI FL 1 Top Do...

Page 11: ...ace the recommended BTU size for your building If you have a Hot Air Regulator set at high and furnace does not heat properly shorten chain one or more notches Do not exceed 600 degrees on top of furnace Overheating will damage furnace Use seasoned wood ONLY Wet wood robs the energy that normally distributes through the building Recommended 20 or less moisture 3 Problem Excess smoke or flames comi...

Page 12: ...ion of the furnace The owner is responsible for labor and costs to complete the repair The owner may at his op tion and with D S Stoves approval have the furnace shipped to the factory for repair All labor and material costs for repair at the factory will be borne by D S Stoves The owner is responsible for all shipping costs D S Stoves gaskets paint or enameled parts firebrick and furnace cement a...

Reviews: