background image

21

For your nearest Roots office contact information, please consult the last page of this document.

temporary protective screen as described under 
INSTALLATION is strongly recommended.

J

Recheck blower leveling, drive alignment and 
tightness of all mounting bolts if installation is not 
recent. If belt drive is used, adjust belt tension 
correctly.

J

Turn drive shaft by hand to make sure impellers 
still rotate without bumping or rubbing at any point.

J

Ensure oil levels in the main oil sumps are correct.

J

Check lubrication of driver. If it is an electric motor, 
be sure that power is available and that electrical 
overload devices are installed and workable.

J

Close the three drain line valves in the bottom of 
cylinder (VERTICAL BLOWER ONLY).

J

Open the manual unloading valve in the discharge 
air line. If a valve is in the inlet piping, be sure it is open.

J

Bump blower a few revolutions with driver to check 
that direction of rotation agrees with arrow near 
blower shaft, and that both coast freely to a stop.  Do
not restart the blower until it has come to a complete
stop.

J

Turn on sealing water supply by opening the manual
shut-off valve (C in Figure 3f). Water will not flow to the
spray nozzle yet since solenoid operated valve (SV) is
electrically held closed until de-energized by the motor
starter.

J

Set valving at the water flow meter (Figure 3) so meter
is in the line, with the by-pass pipe loop closed. Set
spray control valve (b) about 1/4 open as a preliminary
adjustment. In a two-stage installation, also set corre-
sponding valve (A) at the second blower in the same
manner.

With the preceding checks and adjustment completed satis-
factorily, the vacuum blower should be ready for an operat-
ing tests. The following procedure is recommended:

A.  Start the blower, let it accelerate to full speed, then shut

off. listen for knocking sounds, both with power on and
as the unit slows down. Also observe the sealing water
flow meter. A flow indication verifies that solenoid valve
(SV) has opened properly.

B.   If no problems have appeared, restart the blower and let

it operate for 5 to 10 minutes under no-load conditions.
Adjust spray control valve (B) so that the water flow
meter show a rate in gallons per minute equal to the
Recommended Rate in Table 1d in this section. For a
two-stage installation, close valve (B) on first stage and
adjust valve (A) on second stage so that flow meter indi-
cates one-third of the allowable total flow rate. Then
open valve (B) until flow meter reads the correct total
water rate. This adjustment is semi-permanent, and the
two control valves should be locked by removing their
wheels or by other suitable methods. Valve (C) then
serves as the master valve.

C.  Also during this period, check the cylinder and head-

plates for hot spots indicating impeller rubs. Continue to
be alert to unusual noises and changes in vibration.
Check oil levels in the sight windows at both sumps, and
verify several times theat the flow rate at the sealing
water meter remains reasonably constant.Shut unit down
and note whether water meter shows no flow, indicating
the solenoid water valve (SV) has closed properly. Open
valves in cylinder drain lines (vertical blower only) and
make sure lines are not clogged. Close valves after drain-
ing. Recheck all surface for hot spots.

D.  If all conditions are acceptable, restart the vacuum blow-

er and observe operation for at least one hour. During
this period the normal vacuum working load should be
applied on the blower inlet gradually. As this is done, it is
important to make sure the inlet vacuum level and the
temperature rise do not exceed the allowable figures list-
ed in Table 1d in this section.  Mercury manometers
should be installed at the inlet and discharge of the blow-
er to check pressure conditions. On two-stage units they
should be installed for both blowers.

Operating temperatures under average conditions will be low
enough that  sufficient check can be made by feeling the
cylinder. However, if the cylinder temperature runs uncom-
fortably hot, it may be adisable to install inlet and discharge
thermometers for more accurate information. As the run pro-
gresses, continue to check for noises and vibration changes,
observe il levels in the sight glass at each sump, and watch
the water flow rate. Also note the behavior of the discharge
silencer drain trap. If any troubles appear, refer to the TROU-
BLESHOOTING CHECKLIST, page 12, as well as the items at
the bottom of this page for suggested remedies.

The vacuum blower should now be ready for continuous duty
under full working load. During the first several days make
periodic checks to be sure that all conditions remain reason-
ably steady and within specified limits. These checks can be
especially important if the unit is part of a process system in

Trouble

Possible Cause

Remedy

Excessive power

Excessive power

Vibration

Excessive water flow  

Pressure unbalance (2-stage pump)

Water build-up in cylinder at start

Compare flow meter rate with table 1a, determine whether
water process has increased

Check interstage valve and piping for leakage

Clean out cylinder drainline and make sure outlet end is not
submerged

Additional Troubleshooting for VJ Blowers

Summary of Contents for ROOTS DPJ Series

Page 1: ...r Contents GENERAL INFORMATION 1 12 Information Summary 1 Safety Precautions Operating Limitations 3 Operation 4 Installation 5 9 Lubrication 10 Inspection Maintenance 11 Troubleshooting 12 J Check shipment for damage If found file claim with carrier and notify Roots J Unpack shipment carefully and check contents against Packing List Notify Roots if a shortage appears J Store in a clean dry locati...

Page 2: ...subject to the current General Terms of Sale GTS 5001 and Warranty Policy WP 5020 Copies are available upon request Contact your local Roots Office or Roots Customer Service Hot Line 1 877 363 ROOT S 7668 or direct 832 590 2600 ...

Page 3: ...ese limits apply to all units of normal con struction when operated under standard atmospheric condi tions Be sure to arrange connections or taps for instruments such as thermometers and pressure or vacuum gauges at or near the inlet and discharge connections of the unit These along with a tachometer will enable periodic checks of oper ating conditions PRESSURE The pressure rise between inlet and ...

Page 4: ...ovided and that thermometers be in both inlet and discharge lines Readings from these instruments will show whether pressure or temperature ratings of the blower are being exceeded During the final run check operating conditions frequently and observe the oil levels at reasonable intervals If excessive noise or local heating develops shut down immediately and determine the cause If either pressure...

Page 5: ... Test them first for tightness and fractures by tapping with a hammer In lifting keep the direction of cable pull on these bolts as nearly vertical as possible If lifting lugs are not available lifting slings may be passed under the cylinder adjacent to the headplates Either method prevents strain on the extended drive shaft Packaged Units When the unit is furnished mounted on a baseplate with or ...

Page 6: ...ation must be estab lished accordingly and is indicated by an arrow near the shaft Typical arrangement on vertical units has the drive shaft at the top with counterclockwise rotation and discharge to the left Horizontal units are typically arranged with the drive shaft at the left with counterclockwise rotation and discharge down See drawings on page 9 for other various unit arrangements and possi...

Page 7: ...7 For your nearest Roots office contact information please consult the last page of this document Acceptable Blower Drive Arrangement Options ACCEPTABLE UNACCEPTABLE ...

Page 8: ...usefulness has ended as the wire will eventually deteriorate and small pieces going into the unit may cause serious damage Pipe flanges or male threads must meet the unit connections accurately and squarely DO NOT attempt to correct misalign ment by springing or cramping the pipe In most cases this will distort the unit casing and cause impeller rubbing In severe cases it can prevent operation or ...

Page 9: ...9 For your nearest Roots office contact information please consult the last page of this document Blower Orientation Conversion RAM WHISPAIR units ...

Page 10: ...es table on this page Roots synthetic oil Roots P N 813 106 is specified Roots does NOT recommend automotive type lubricants as they are not formulated with the properties mentioned above The oil level should not fall below the middle of the site gauge when the blower is idle It may rise or fall on the gauge dur ing operation to an extent depending somewhat on oil tem perature and blower speed Pro...

Page 11: ...ces Sudden bearing failure is usually more serious Since the shaft and impeller are no longer supported and properly located exten sive general damage to the blower casing and gears is likely to occur Oil seals should be considered expendable items to be replaced whenever drainage from the headplate vent cavity becomes excessive or when the blower is disassembled for any reason Some oil seal leaka...

Page 12: ...questionable 16 Excessive belt tension Readjust for correct tension Vibration 17 Misalignment See Item 15 18 Impellers rubbing See Item 10 19 Worn bearings gears Check gear backlash and condition of bearings and replace as indicated 20 Unbalanced or rubbing Scale or process material may build up on casing and impeller impellers or inside impellers Remove build up to restore original clearances and...

Page 13: ...purge gas pressure in the vent chamber should be maintained at about 1 psi over the discharge pres sure The plugged drain connections are provided to allow periodic draining of any fluid which might accumulate in the seal chamber This can be a combination of lubricating oils liq uids entrained in the process gas or condensables from the process gas Care must be used when opening the vent drain plu...

Page 14: ...133 18 1241 16 539 409 4 5 4000 240 133 18 1241 16 539 412 4 5 4000 240 133 15 1034 16 539 418 4 5 4000 240 133 10 690 16 539 616 6 0 3000 230 128 15 1034 16 539 624 6 0 3000 230 128 10 690 16 539 Table 1a RAM G RAM GJ Blower Maximum Allowable Operating Conditions Frame Gear Speed Temp Rise Delta Pressure Inlet Vacuum Size Diameter Inch RPM F C PSI mbar INHG mbar ...

Page 15: ... permanent cover and silencer locations may be exchanged if the installation requires The permanent cover must be removed both jet plenums inspected and cleared of foreign material then the perma nent cover and silencer installed in the desired locations before operating Full size jet and discharge silencers are desirable however the jet silencer may be reduced one nom inal size providing either t...

Page 16: ...16 Figures 3b DVJ VACUUM SYSTEM SCHEMATIC For DVJ Applications ...

Page 17: ...dures are for coating new uncoated repair parts spot repair of coating or renewal If setting clearances and timing are involved this should be done before the new parts are coated Subsequent cleaning and coating may involve at least partial disassembly for proper cleaning without damaging the coating of other original parts still coated and to apply coating properly Normally for new uncoated surfa...

Page 18: ... hard to turn initially as a result Turn over by hand until the running is free Do not try to free up the blower by coupled or belted drive and do not try to spin the rotors with shop air Do not attempt to use any kind of solvent or cleaner to partially remove coating as this could ruin all of the coating If necessary coating can be scraped for such partial removal Complete Removal of Coating This...

Page 19: ... for eign material before installing the return cooled air piping full port size piping must be used Inspect the cooler for foreign material before installation as dirt metal shavings paper and other materials could restrict air flow to the blower jets or damage close clearance rotating parts within the blower Operation NOTE be sure the pressure drop between the blower dis charge and the return ai...

Page 20: ...e converted from water sealed operation to use as a dry vacuum blower all scale or dirt deposits must first be completely removed from all internal surfaces Operating Limitations To establish and maintain continued satisfactory perform ance a ROOTS VJ vacuum blower must be operated within certain approved limiting conditions The Manufacturer s warranty is contingent on such operation Maximum limit...

Page 21: ...ect total water rate This adjustment is semi permanent and the two control valves should be locked by removing their wheels or by other suitable methods Valve C then serves as the master valve C Also during this period check the cylinder and head plates for hot spots indicating impeller rubs Continue to be alert to unusual noises and changes in vibration Check oil levels in the sight windows at bo...

Page 22: ... for dirt removal the blower may be reconnected and a check run made to veri fy normal operation Before operating under power turn the drive shaft several revolutions manually to verify that impellers turn freely at all points with no scrapping or or bumping Also make sure that tape is removed from the drain vent holes near the bottom of each headplate Scale build up A basic principle of the ROOTS...

Page 23: ...J Single Vacuum Blower scale is primarily organic Where the scale composition is primarily mineral or is unknown samples of the material should be checked and specific recommendations request ed from the scale removal suppliers Strong acid com pounds or other corrosion causing materials should be avoided because of the harm which will result to the internal surfaces and clearances of the blowers ...

Page 24: ...24 NOTE Only if 2 stage exhauster Figure 3f Seal Water Control Piping Diagram Figure 3g Installation of Two Stage VJ 2 Vacuum Blower ...

Page 25: ...ng 65467023 1 Headplate 2 2 Spray nozzle assembly 1 3 Gearbox 1 4 Gear Assembly 1 5 Drive End Cover 1 7 Gasket 2 8 Nameplate 1 9 Lubrication Label 2 10 Shim Set 1 11 Cylinder 1 12 Impeller Shaft Drive 1 13 Impeller Shaft Driven 1 14 Bearing Roller 4 16 Pin Dowel 4 17 Dri Lok Pin 2 19 Key 1 20 Drive Screw 2 21 Plug Vent 2 22 Drain Filler Plug 4 23 Capscrew 400 34 23 Capscrew 600 40 27 Seal Lip Head...

Page 26: ...26 Assembly of RAM Series Air Gas Blowers ...

Page 27: ...27 For your nearest Roots office contact information please consult the last page of this document Assembly of Series RCS V ...

Page 28: ...877 363 ROOT S 7668 Direct Phone 832 590 2600 Connersville Indiana Operations U S Toll Free Phone 1 877 442 7910 Direct Phone 765 827 9285 United Kingdom Operations Phone 44 0 1484 422 222 USA Canada Sales Phone 773 444 3360 Houston Texas Factory Service Phone 713 896 4810 Mexico City Sales and Factory Service Phone 52 55 5889 5811 Dubai Sales and Factory Service Phone 971 4 8830831 Malaysia Sales...

Reviews: