7400 Series CE End Drive Conveyors
Installation
Installation
Figure 3
Required Tools
• 17 mm wrench (for hexagonal head fasteners)
• 4 mm hex wrench (for bearing shaft assembly fasteners)
• Level
• Torque wrench
Recommended Installation
Sequence
1.
Attach the stands to the conveyor. Refer to “Stand
Installation” on page 9.
2.
Attach the tail assemblies to the frame. Refer to “Tail
Assembly Installation” on page 10.
3.
Attach the lifters, if applicable. Refer to “Lifter
Installation” on page 14.
4.
Install the gearmotor, if applicable. Refer to the “7400
Series Drive Package Installation, Maintenance and
Parts Manual.”
5.
Attach the wear strips. Refer to “Wear Strip
Installation” on page 14.
6.
Install the belt. Refer to “Belt Installation” on page 15.
7.
Attach the belt returns. Refer to “Belt Return
Installation” on page 16.
8.
Attach any guides / accessories. Refer to the "Service
Parts" section starting on page 28.
Conveyors Longer than 3048 mm
Typical Connection Components
.
Figure 4
1.
Locate the section number sequence etched on each
section of frame
.
Figure 5
2.
Position the frame sections in the correct order.
CAUTION
CAUTION
Dorner recommends cleaning all the “food
zones” prior to placing conveyor into service.
Ensure adequate access is provided for
cleaning and servicing equipment so that the
required level of hygiene can be maintained.
CAUTION
CAUTION
Conveyor MUST be mounted straight, flat,
and level within confines of conveyor. Use a
level (Figure 3, item 1), during setup.
1
1
M10 x 1.5 mm hex head cap screws (x4)
2
Connector hex rods (x2)
3
Conveyor frames
3
1
2
1
2
3
1