Disassembly and Reassembly of Major Components
- 45 -
3. Disassembly and Reassembly of Major Components
3.1. Engine Disassembly
●
Engine parts' disassembly procedures are as follows;
3.1.1. General precautions
●
For the various tool storage before disassembly and parts storage after disassembly, the shelf for
parts is prepared.
●
At the time of disassembly and reassembly, do the work with the naked and clean hand, and also
the working place must be maintained clean.
●
The torn parts after disassembly must be kept not to collide each other.
●
In disassembling, torn parts should be laid in disassembled order.
●
Always close all the fuel valves before serving the system.
3.1.2. Oil level gauge
●
Take out the oil level gauge.
3.1.3. Engine oil
●
Turn the valve opening and then move
the oil drain pump lever as figure by
hand, and let engine oil discharge into the
prepared vessel.
EE3OM023
EE3OM015
Engine oil drain pump
Summary of Contents for GV158TIC
Page 1: ...950106 058010EN GV158TIC GV180TIC GV222TIC GAS GENERATOR ENGINE Operation Maintenance Manual...
Page 2: ......
Page 6: ...6 Engine Installation 143 6 1 Installing 143 6 2 Inspection Prior to Installation 144 Appendix...
Page 130: ...Electrical equipment 124...
Page 148: ...Maintenance of major parts 142...
Page 152: ...Engine installation 146...
Page 162: ...Appendix 156...