9000-065-J-9-11
15
1.5 Concrete Pad Setup or Post Mounting
Concrete Pad Setup
Top View
Side View
Side View
24”
24”
16.5”
Minimum Concrete Pad
Extended Concrete Porch
(Work Area)
Base Plate
Operator
Attachment
Hardware
2 Posts
Underground depth of
the concrete pad is
determined by soil
conditions and local
building codes.
Reinforced concrete
recommended.
Concrete pad
MUST be level.
Base Plate
MUST be level.
8”
Conduit
Area
Concrete Pad
Center
13”
2”
2”
2”
3.75”
4.5”
3.5”
3.75”
4”
Minimum
2.5”
12”
12”
12”
7”
Conduit
4” min. above ground.
Gate
Concrete Pad
Optional Post Mount Kit
DoorKing offers a post mount kit specifically for
the Model 9000 (P/N 9000-015). The kit
includes a base plate, 2 posts and hardware to
attach the operator to the base plate. This kit
will raise the operator and allow different chain
heights for specific operator applications. Refer
to the instruction sheet provided with the kit for
concrete foundation size, conduit type and
placement. This kit is needed if a chain tray is
required to support the chain’s weight when a
longer gate is used (See page 18 for more
information about DoorKing’s chain tray kit).
Gate
Optional
Chain Tray
Kit
Gate
Wall
4”
Concrete Foundation
Underground depth of the concrete
foundation is determined by soil
conditions and local building codes,
18” minimum depth. Reinforced
concrete recommended.
Operator must be 4” minimum.
3/4” conduit
with sweeps.
18”
Min.