OPERATOR INSTALLATION
6
4.2. Requirments to door installation
Prior to installation check if the door is properly bal-
anced and moves smoothly when automatically oper-
ated.
Make sure, that minimal clearance between the ceiling
and the top point, when the door is moving, is not less
than 45 mm (pic. 1).
Check, that the door leaf top roller is in the horizontal
part of the guide rail, when the door is completely closed
(pic. 2).
4.3. Connection of operator and guide
1. Motor shaft
2. Bushing
3. Guide
4. U-bracket
5. Tapping screws
1. Put the operator bushing (4) on the shaft (5).
2. Insert the operator unit into the hole on the guide (3).
3. Fasten the operator with U-brackets (2) and tapping
screws (1).
Pic. 1
Pic. 2
45 мм
4. OPERATOR INSTALLATION
1.
Set of spanners
2.
Set of slotted and cross screwdrivers
3.
Set of drills for metal
4.
Set of drills for concrete
5.
Pliers
6.
Hacksaw for metal
7.
Electric drill
8.
Tape measure (folding rule)
1
2
3
4
5