JT520 Operator’s Manual
Conduct a Bore - 79
Correct Direction
CMW
Correct Direction
Correcting direction is a skill operators gain with experience and knowledge of equipment and soil
conditions. These instructions cover only basic procedures. For information about specific equipment or
jobsites, contact your Ditch Witch dealer.
To track progress and make corrections, one crew member locates the drill head and sends instructions to
the operator. Corrections are made by tracking the drill head, comparing current position to bore plan, and
steering drill head as needed.
Basic Rules
•
Steering ability depends on soil condition; bit, drill head, and nozzle used; roll of drill head; and
distance pushed without outer rotation.
•
All corrections should be made as gradually as possible. See “Recommended Bend Limits” on
page 51.
•
Over correcting will cause “snaking.” This can damage pipe and will make drilling and pullback more
difficult. Begin to straighten out of each correction as early as possible.
•
Do not push an entire piece of drill pipe into ground without rotation. This can exceed bend radius and
cause pipe failure.
Procedure
1.
Locate drill head. Take readings available with your beacon and locating equipment such as:
•
depth
•
pitch
•
left/right information
•
temperature
•
beacon roll
2.
Compare position to bore plan. Determine direction drilling should go.
3.
Position drill head.
4.
Push in drill pipe as needed to change direction.
5.
Rotate in remaining length of drill pipe.
Summary of Contents for JT520
Page 1: ...JT520 Issue 1 1 Operator s Manual CMW 053 1219...
Page 59: ...Prepare 58 JT520 Operator s Manual Check Supplies and Prepare Equipment CMW...
Page 63: ...Drive 62 JT520 Operator s Manual Shut Down Unit CMW...
Page 71: ...Transport 70 JT520 Operator s Manual Tow CMW...
Page 113: ...Systems and Equipment 112 JT520 Operator s Manual Drill Pipe CMW...
Page 117: ...Complete the Job 116 JT520 Operator s Manual Stow Tools CMW...
Page 141: ...Service 140 JT520 Operator s Manual As Needed CMW...
Page 145: ...Specifications 144 JT520 Operator s Manual CMW...
Page 148: ......
Page 149: ......
Page 150: ...JT520 Operator s Manual Service Record 149 CMW Service Record Service Performed Date Hours...
Page 151: ...CMW Service Record 150 JT520 Operator s Manual Service Performed Date Hours...