Directive Systems & Engineering DSE3-50 Manual Download Page 3

P a g e

 | 

 

 

DSE3-50 Rev 6/20 

PARTS LIST 

Note:  All hardware is Stainless Steel unless otherwise noted.

 

 

 

Unpack the antenna kit and check each part against the following list. Do not throw any packing 
material away until the antenna is completely assembled and ready for final installation. Some parts 
may be packed inside boom sections. 
 
The box in which the antenna was shipped contains the following items: 

 

 

6’ boom section 

Boom to mast plate 

Element halves (R, DE, D) 

3  

Element couplers 

48

” T-arms 

Connector bracket assembly 

Balun 

Anti Seize Compound 

 
Hardware Bag 
 

 
 

 
 

 

  

 
 

 

 

Boom-to-Mast Hardware 

T-arm shorting bars 

8-32 x 1¼

” Machine screws 

#8 Nuts 

#8 Split lock washers 

#8 Internal tooth lock washers 

6-

32 x ½” Machine screws 

#6 Internal tooth lock washers 

½” U-bolts 

¼” Locknuts 

¼” x 1 ¾” U-bolts 

¼” Nuts 

¼” Lock washers 

¼” Flat washers 

5/16” U-bolts 

5/16” Nuts 

5/16” Lock washers 

5/16” Flat washers

Element saddles 

½” Element End caps 

3/8” T-arm End caps 

1 3/8” End caps 

Cable ties 

 

Anti-Seize Compound

 - Apply a small amount to the aluminum joints to prevent the aluminum from 

oxidizing and to the threads of the U-Bolts to prevent galling.

 

 

 

ANTENNA ASSEMBLY   

   

 

1. 

Locate the 6’ boom section and, using a permanent marker (refer to Figure 1), place a mark 2 ¼” 
from one end of the boom 

– this is the Reflector point. All further measurements are made from 

this end of the boom. Next

, place a mark at 42 ¼” – this is the Driven Element point. Next, place a 

mark at 34 

¼” – this is the center line of the boom-to-mast plate. Last, place a mark at 69 ¾” – this 

is the Director.  

 

If this DSE3-

50 has the rear mount option, place a mark 3 7/8” from the end of the main boom. 

Slide the 12” piece of 1 ½” tubing to this line, with the slits over the boom. 
 

Reviews: