5.
Start-up operation
5.1 Staff
After opening the terminal cover, there is the risk of con-
tact with live parts which can lead to serious or fatal inju-
ries.
For this reason, only qualified service personnel being
aware of this risk must perform the meter installation.
Install the meter according to the following steps.
5.2 Installation
Checking if the mains voltage complies with the
meter voltage and if the power to be captured is
smaller or equal as the maximum meter power.
These values are printed on the rating plate of
the meter.
Connecting the meter to the power supply accor-
ding to the wiring diagram which is attached to
the terminal block. Tighten the clamp screws
with a torque of < 2.3 Nm.
The display elements must be checked when the
meter is connected.
A small bar is shown in the LCD display, when
the load current is lager as the starting current
of the meter.