Electrovap MC
Final inspection continued
Installation
27
Steam Distribution Hose/Pipe
1.
Inspect the steam distribution pipe and ensure there are no
horizontal runs.
2.
If flexible steam hose is used check the overall length is less
than 3m.
3.
If copper pipe is used check the effective length is less than
6m..
4
. Check the steam distribution hose/pipe is the correct size.
5.
Inspect the flexible steam hose fittings and ensure they are
secured and they will prevent the hose from sagging..
6.
Check copper pipe is insulated.
7.
Check there is at least 500mm of straight steam hose on the
outlet of the humifier.
8.
Check hose clips have been fitted and secured.
Steam Distribution Pipe
1.
Check the location of steam distribution pipes have been
positioned in accordance with the dimensions shown in the
installation section.
2.
Check that steam distribution pipes have been positioned in
accordance with the dimensions pipes over 290mm long have
been supported adequately.
Condensate Hose
1.
Visually inspect the condensate hose to ensure the
following:
a)
The condensate hose is secured firmly to the condensate
outlet on the steam distribution pipes.
b)
There is a trap in the condensate hose.
c)
There is a fall of 45° away from the steam distribution pipe.
d)
The condensate h
ose ends to waste waters.
FAN DISTRIBUTION UNIT
1.
Check the correct clearances have been observed around
the unit.
2.
Check the correct electrical connection has been made
inside the humidifier electrical connection.
3