Step 5: 

Rotate the selector knob clockwise to the “HIGH 

PASS” position at the end of the green pass sector.  The 

monitor’s corresponding green “OPR1” or “OPR2” LED 

should remain illuminated.

Step 6: 

Rotate the selector knob clockwise to the “HIGH 

FAIL” position.  The monitor’s corresponding green “OPR1” 

or “OPR2” LED should turn off and the red LED should 

illuminate and the alarm should sound.

Step 7: 

Disconnect the Monitor Calibration Unit from the 

satellite remote.

Step 8: 

Repeat this procedure for the remaining satellite 

remote.

TESTING THE MAT CIRCUIT
Step 1:

 Connect the Calibration Unit’s banana plug wire 

labeled “GROUND” to a known ground.

Step 2:

 Connect the included stacking snap to the banana 

plug labeled “MAT” on the Calibration Unit.  Disconnect the 

satellite remote from its mat connection and re-install it to the 

Calibration Unit’s stacking snap (see Figure 5).

Note:

 The stacking snap must be isolated from the grounded 

mat.

Note:

 During FAIL LOW and FAIL HIGH, the monitor will 

continuously alarm until the banana lead is removed from the 

satellite remote.  The alarm will shut off approximately 8-10 

seconds after the removal of the banana lead.

Step 5: 

Repeat this procedure for the remaining satellite 

remote.

Calibrating the Jewel

®

 Workstation Continuous 

Mini Monitor

The Jewel

®

 Workstation Continuous Mini Monitor is available 

as following item numbers:

Figure 5. Connecting the MAT test lead from the Monitor 
Calibration Unit to the satellite remote

Step 3: 

Rotate the Calibration Unit’s knob switch to the MAT 

FAIL 10M position.  The monitor’s corresponding red “MAT1” 

or “MAT2” LED should illuminate and the alarm should 

sound.

Step 4: 

Rotate the selector knob counter-clockwise to the 

MAT PASS 10M position.  The monitor’s corresponding 

“MAT1” or “MAT2” green LED should illuminate.

Item

Voltage

19212

120 VAC

TESTING THE OPERATOR CIRCUIT

Step 1:

 

Connect the Calibration Unit’s banana plug wire 

labeled “GROUND” to a known ground.

Step 2: 

Insert the Calibration Unit’s banana plug labeled 

“OPERATOR” into the jack labeled “OPERATOR” on the 

Jewel

®

 Workstation Continuous Mini Monitor (see Figure 6).

Figure 6. Connecting the OPERATOR test lead from the 
Monitor Calibration Unit to the Jewel

®

 Workstation 

Continuous Mini Monitor

Step 3: 

Start the Calibration Unit’s selector knob at the full 

counter-clockwise position and power the monitor.  When 

testing the OPERATOR circuit, test only the first four limits 

on the Calibration Unit.  Rotate the selector knob to the 

“LOW FAIL” position; the red “OPERATOR GROUND” LED 

on the monitor should illuminate and alarm.

Summary of Contents for TB-2082

Page 1: ...brand equipment The following step by step procedures will cover calibration for specific test units The procedures will not cover adjustment of the test equipment For detailed information regarding adjustment of specific Desco brand testers contact our Customer Service Department at 909 627 8178 TECHNICAL BULLETIN TB 2082 Calibrating the Full Time Continuous Monitor The Full Time Continuous Monit...

Page 2: ...uous Monitor Step 3 Rotate the Calibration Unit s knob switch to the MAT FAIL 10M position The monitor s red MAT GROUND LED should illuminate and the alarm should sound Step 4 Rotate the selector knob counter clockwise to the MAT PASS 10M position The monitor s MAT GROUND green LED should illuminate Item Voltage 19232 120 VAC 19233 220 VAC Note If calibrating discontinued items 19208 or 19209 disc...

Page 3: ...nana lead Step 5 Repeat this procedure for the remaining satellite remote Calibrating the Jewel Workstation Continuous Mini Monitor The Jewel Workstation Continuous Mini Monitor is available as following item numbers Figure 5 Connecting the MAT test lead from the Monitor Calibration Unit to the satellite remote Step 3 Rotate the Calibration Unit s knob switch to the MAT FAIL 10M position The monit...

Page 4: ...tion The monitor s red WORKSURFACE GROUND LED should illuminate and the alarm should sound Step 4 Rotate the selector knob counter clockwise to the MAT PASS 500M position The monitor s WORKSURFACE GROUND green LED should illuminate Note During FAIL LOW and FAIL HIGH the monitor will continuously alarm until the banana lead is removed from the satellite remote The alarm will shut off approximately ...

Page 5: ...us Mini Monitor 19213 19214 19215 19216 19217 Multi Mount Continuous Monitor 19220 19221 19222 19223 98225 98226 98227 98228 Calibration Required Test Equipment RLC Bridge Settings For 50 Hz Frequency 1 000 Hz 20 x 50 20th Harmonic For 60 Hz Frequency 1 020 Hz 17 x 60 17th Harmonic Set function switch to read equivalent parallel circuit Additional Required Test Equipment for 98220 MAT Resistance M...

Page 6: ...roximately two weeks If your unit is out of warranty call our Customer Service Department at 909 627 8178 Chino CA or 781 821 8370 Canton MA for a Return Material Authorization RMA and proper shipping instructions and address Desco will quote repair charges necessary to bring your unit up to factory standards Warranty Exclusions THE FOREGOING EXPRESS WARRANTY IS MADE IN LIEU OF ALL OTHER PRODUCT W...

Reviews: