Figure 2. Mounting Location from Front and Back of Rack
1.
Location for the clip nuts to secure the top cover
2.
Location for the clip nuts to secure the expansion
enclosure
3.
Location for the expansion enclosure rack rails
4.
Location for the 1U cable management tray rails
Mount the Cable Management Tray
If you plan to use the 1U cable management tray, mount the tray before mounting the SC460 expansion enclosure.
Prerequisite
Required materials:
•
Screwdriver (034-000-193)
•
Four 8-32 x 0.75 in. knurled head Phillips screws (036-034-012)
•
Left 1U cable management tray rail (042-034-012)
•
Right 1U cable management tray rail (042-034-008)
•
1U cable management tray (042-033-060)
Steps
1.
Adjust the length of the 1U cable management tray rails (042-034-012 and 042-034-008) to fit the rack.
2.
Align the rails so that the UP arrow is pointed in the correct direction and the side of the rail labeled FRONT is at the front of
the rack.
3.
Insert the alignment pins of left and right rails into the mounting holes at the front and back of the rack.
4.
Secure the rails by installing 8-32 x 0.75 in. screws (036-034-012) into the holes at the front and back of the rails.
5