Chapter 3.
Installing the Rack Cabinet
3-7
3.5.
Inspecting the Cabinet
Once the cabinet has been unpacked, a preliminary visual inspection must be
performed before it is unloaded from the shipping pallet.
C007
CAUTION
C007:
Preequipped rack cabinet:
If the inspection indicates an unacceptable safety condition, the
condition must be corrected before powering on the system and/or
devices inside the rack cabinet.
Required Tools
None
Procedure
1. Check that the delivery is compliant with the Purchase Order.
2. Check that the boxes labeled
Open Me First
and
Unpacking Box
contain
the stabilizer and skate-board assemblies.
3. Check covers and doors for sharp edges, damage or alterations.
4. Check the correct fit of covers and doors.
5. Open the front and rear doors.
Note
Unlock the front door with the key, pull the handle forwards and
upwards to disengage the lock.
6. Check for internal damage, alterations and obvious safety hazards such as
broken wires, sharp edges, or broken insulation.
7. Check internal cables for damage.
8. Check for dirt, water, and any other form of contamination inside the
cabinet.
9. Check the voltage label on the back of the cabinet to ensure that it matches
the voltage at the power outlet.
10. Carefully check the electrical specifications on the safety labels at the back
of the cabinet.
Summary of Contents for M3S2G8
Page 4: ......
Page 20: ......
Page 80: ...5 4 Installation and Service Guide 5 Proceed in the same way from the rear of the cabinet ...
Page 84: ...5 8 Installation and Service Guide 5 Proceed in the same way from the rear of the cabinet ...
Page 96: ......
Page 100: ......
Page 106: ......