N3200-ON Series switch installation
To install the N3200-ON Series switch, complete the installation procedures in the order that is presented in this chapter.
Always handle the switch and components with care. Avoid dropping the switch or its field replaceable units (FRUs).
NOTE:
ESD damage can occur if components are mishandled. Always wear an ESD-preventive wrist or heel ground strap
when handling the N3200-ON Series switch and components. As with all electrical devices of this type, take all the
necessary safety precautions to prevent injury when installing this switch.
Topics:
•
•
Rack or cabinet hardware installation
•
•
•
Two-post five-inch-offset full-width switch installation
•
Two-post flush-mount full-width switch installation
•
Wall-mount full-width switch installation
•
•
1U Tool-less mount ReadyRails installation
•
Flush-mount ReadyRail installation
•
Center-mount ReadyRail installation
•
Four-post threaded ReadyRails installation
•
•
•
•
Unpack
NOTE:
Before unpacking the switch, inspect the container and immediately report any evidence of damage.
When unpacking the switch, ensure that the following items are included:
•
One N3248P-ON or N3248PXE-ON Series switch
•
One RJ45 to DB-9 female cable
•
One MicroUSB console cable
•
Two sets of rack mounting brackets and screws
•
DC only: ground lug and screws
•
Four rubber feet
•
N3248PXE-ON only: DC ground lug kit
•
One pluggable AC PSU
•
Three pluggable fan units
•
One AC power cable, country or region specific
•
DC only: DC power cables
•
N3200-ON Series Quick Setup Guide
•
N3200-ON Series Warnings Guide
•
Safety and Regulatory Information
•
Warranty and Support Information
4
16
N3200-ON Series switch installation