STARTUP REQUIREMENTS
The following items are required and must be completed
before startup can be performed by the manufacturer’s
representative.
1. All installations and wiring diagrams must
be studied and understood before
proceeding with the installation. If there
are any questions contact the factory.
2. All wiring must be completed.This
includes main power, control and
sensors.
3. All refrigeration and/or water piping must
be completed.
4. All additional refrigerant required per
instuctions must be added.
5. Proper water flow, if required must be
established.
6. Duct work, including duct, grills and
diffusers must be completed.
7. A thorough leak check should be
performed. Due to the fact that the unit
may be damaged while in transit we
recommend that all field and factory
connections be leak checked.
In addition a refrigeration mechanic from the installing
contractor must be on site with the following tools.
1. Manifold set/or sets for pressure
readings.
2. Air flow meter/s. Magnehelics in the
ranges 0 to 1.0 in. w. c. and 0 2.0 in. w. c.
3. Volt-Ohm-Amp meter/s.
4. Temperature meters with probes and
strap on bulbs, and sling psychrometer.
5. Assorted refrigeration and standard tools.
6. All maintenance personnel to be
responsible for the unit service should be
made available.