background image

7

Ÿ

Provide an upstream and downstream shut-off valve of high quality and 
with low pressure drop. A valve before the meter will allow local shutoff of 
the water if change or repair is later needed. A valve or check valve on the 
outlet side of the meter will keep water from draining from the building 
when changing or removing the meter. 

Ÿ

Provide a drain cock between the meter and the downstream valve. 

Ÿ

In general, install the meter horizontally in the line to obtain optimum 
performance as shown in Fig 2. Volumetric meters may also be installed 
vertically or at an incline.

Ÿ

Ensure  that  the  installed  meter  will  be  easily  accessible  for  reading, 
inspection, and service. 

Ÿ

Protect the meter and piping against flooding, mechanical damage and 
tampering. 

Ÿ

The installed meter must not be an obstacle or a hazard to the customer or 
interfere with public safety. 

Ÿ

Always flush the upstream and downstream piping prior to installation. 
Ensure that the water in the pipes is completely free of debris.

4.  OPERATION AND MAINTENANCE

1

2

5

7

Figure one

 )

6

Inlet

4

3

2

3

4

5

6

7

≥5D 

≥10D 

1. Water meter
2. Nut
3.Gasket 1
4. Gasket 2

5. Pipeline
6. Gasket 3
7. Screw

WP Bulk Water Meter

Fig 3

Summary of Contents for MJ

Page 1: ...WATER METERS Installation Operating Manual MJ PD WP...

Page 2: ...SPECIFICATIONS 1 1 2 SYMBOLS WARNINGS 3 INDEX Davis Shirtliff Ltd 2020 Contents herein are not warranted 3 INSTALLATION 4 4 OPERATION MAINTENANCE 7 5 TERMS OF WARRANTY 9...

Page 3: ...r DN15 and DN20 sizes and brass for larger sizes Meters are supplied with inlet strainers and union connectors PD Rotary piston type meters that provide high accuracy over a wide flow range The mechan...

Page 4: ...9999 999999 40 0 2 1 15 1 5 3 15 10 40 0 2 1 20 2 5 6 10 3 5 5 12 20 7 50 120 200 70 16 16 16 16 40 40 40 40 0 25 0 24 0 2 0 25 1 1 0 9 1 1 20 2 5 5 25 16 40 0 25 1 50 15 30 7 5 16 50 2 0 02 0 08 65 2...

Page 5: ...lic CAUTION Instructions should be carried out by a qualified professional with parts equipment approved by the local codes and regulations WARNING Meter must not be used as a lever or crowbar to stra...

Page 6: ...otective packaging to the point of installation Storage temperatures shall remain within the range of 20 C to 60 C avoiding direct sunlight Special fittings and accessories are available to provide ea...

Page 7: ...e properly aligned to avoid cross threading damage stripping to the meter ends This is especially important for the engineered composite polymer meter The best method for properly starting meter coupl...

Page 8: ...lowly to pressurize the downstream consumer side of the system Turn off the consumer faucet when normal water flow occurs Ensuring that all consumer faucets are shut observe the low flow detector in t...

Page 9: ...ance as shown in Fig 2 Volumetric meters may also be installed vertically or at an incline Ensure that the installed meter will be easily accessible for reading inspection and service Protect the mete...

Page 10: ...16 bar If there is a pressure regulator verify that the regulator works and is adjusted correctly The service pipe entering and exiting the meter box should be properly bedded to ensure that it is no...

Page 11: ...bility In lieu of any warranty condition or liability implied by law the liability of Dayliff in respect of any defect or failure of equipment supplied is limited to making good by replacement or repa...

Page 12: ...INS450A 02 20 www davisandshirtliff com...