Chapter 3 Installation
INSTALLATION OF ARMS:
-
Fix the long and short sway arms with hinge axis on the carriage according to the floor layout.
-Install the correspond long and short extension arms and fix with M8
×
12 bolt to avoid slipping.
-Put the adapter to the holes on extension arms (can choose differ height adapter to suit different
height chassis)(see picture 8:)
3.2.9 INSTALLATION OF CONTROL BOX OF WIRES
-Fix the control box on the post with bolt.
-Connect the wires according to electrical diagram and air loop according to air loop diagram.
Only authorized qualified personnel can install the electrical part.
-Open the control box cover first.
-Power connection:
Connect the 3 phase five wires (
3
×
2.5mm
2
+
2
×
1.5 mm
2
) for the power supply to the terminal of
control box according to the circuit diagram.
If for 230V connection, connect to the control box according to the circuit diagram.
-
Connection for the
electromagnetic steel of release:
For detail connection, please see the circuit diagram.
-Up limit switch connection:
For detail connection, please see the circuit diagram.
Bolt limit
Picture 8
Summary of Contents for LJCC2045A
Page 1: ...1 TWO POST LIFT LJCC2045A U Us se er r s s m ma an nu ua al l Manufacturer ...
Page 6: ...6 Chapter 2 Description of machine Picture 2 arm extension drawing ...
Page 15: ...15 7 2 EXPLODED DRAWING OF MAICHINE ...
Page 16: ...16 Circuit diagram 220V ...
Page 17: ...17 Circuit diagram 380V ...