CHECKS AFTER FIRST INSTALLATION
INSTRUCTION MANUAL
25
CHECKS AFTER FIRST INSTALLATION
After the initial installation and before starting up, machine test operations must be car-
ried out by qualified personnel, or under the strict supervision of the person in charge
of the machine safety.
The checks to carry out are listed below:
•
The response time at machine STOP, including the ESPE and machine response
times, must be included in the limits defined in the calculation of the safety dis-
tance (refer to "
Response Time and Scan Cycle Setting" on page 62
).
•
The safety distance between the dangerous parts and ESPE must comply with the
requirements indicated in "
Device Positioning and Minimum Distance Calculations"
. The safety zone must be designed so that the approach towards any
dangerous point of the machine can be possible only passing through it, and the
distance that a person is obliged to cover must be longer than the minimum safety
distance.
•
A person must not remain between safety zone and dangerous parts of the
machine undetected.
•
Access to the dangerous areas of the machine must not be possible from any
unprotected area.
•
Verify the correspondence of all the accessory functions, activating them in the
different operating conditions.
•
The machine builder must define the type and frequency for the checks of the
machine and its safety system based on the risk assessment. Regular checks are
recommended in order to prevent external influences or modification (such as
damage or tampering).
•
Safety checks must be carried out at least annually by qualified personnel only and
must be documented in a traceable manner.
•
To test the detection capability of the device(s), the user can use a suitable test
piece, e.g. an optically dark, opaque cylinder. The effective diameter should match
the configured resolution. Datalogic suggests adopting the following procedure:
Place the test piece on several points at the edges of the safety area. The safety
laser scanner must detect the test piece at each position and go to STOP. The num-
ber and location of sites where the test is performed must be chosen so that
undetected access to the hazardous area is not possible.
Do not attempt to insert the test piece into dangerous parts of the machine
located in the safety area.
Remove the test piece from the controlled area and check that:
-the machine automatically restarts (in case of Automatic restart), OR
-the machine restarts only after receiving the restart command (in case of Manual
restart).
The following pictures are examples of detection capability test (the red areas cor-
respond to the configured Safety Areas).
Summary of Contents for Laser Sentinel
Page 1: ...Laser Sentinel INSTRUCTION MANUAL Safety Laser Scanner ...
Page 18: ...GENERAL VIEW xviii SAFERY LASER SCANNER ...
Page 140: ...122 SAFERY LASER SCANNER APPENDIX B OVERALL DIMENSIONS LASER SENTINEL STAND ALONE MODEL ...
Page 149: ......
Page 150: ......
Page 151: ......