DGS Installation test

As DGS is a digital device with self-monitoring, all internal errors 

are visible via the LED and Modbus alarm messages. 

All other error sources often have their origins in other parts of the 

installation.

For fast and comfortable Installation test we recommend 

proceeding as follows.

Optical Check 

Right cable type used. 

Correct mounting height according to definition in Mounting. 

LED status – see DGS trouble shooting. 

Functional test (for initial operation and maintenance) 

Functional test is done by pressing the test button for more than 

8 sec and observing all connected outputs (Buzzer, LED, Relay 

connected devices) are working properly. After deactivation all 

outputs must automatically return to their initial position 

Zero-point test (if prescribed by local regulations) 

Zero-point test with fresh outdoor air. 

A potential zero offset can be read out by use of the Service tool. 

Trip test with reference gas (if prescribed by local regulations) 

The sensor is gassed with reference gas (for this you need a gas 

bottle with pressure regulator and a calibration adapter). 

In doing so, the set alarm thresholds are exceeded, and all output 

functions are activated. It is necessary to check if the connected 

output functions are working correctly (e.g. the horn sounds, the 

fan switches on, devices shut down). By pressing the push-button 

on the horn, the horn acknowledgment must be checked. After 

removal of the reference gas, all outputs must automatically return 

to their initial position.

Other than the trip testing, it is also possible to perform a 

functional test by means of calibration. For further information, 

please refer to the User Guide. 

Comparing sensor gas type with DGS specification

The replacement sensor specification must match the DGS 

specification. 

The DGS software automatically reads the specification of the 

connected sensor and compares with the DGS specification. 

This feature increases the user and operating security. 

New sensors are always delivered factory-calibrated by Danfoss. 

This is documented by the calibration label indicating date 

and calibration gas. A re-calibration is not necessary during 

commissioning if the device is still in its original packaging (is not 

air-tight protection by the red protective cap) and the calibration 

certificate has not expired. 

Summary of Contents for DGS

Page 1: ...as a safety device securing a reaction to a detected high gas concentration If a leakage occurs the DGS will provide alarm functions but it will not solve or take care of the leakage root cause itself Regular Test To maintain product performance and comply with the local requirements the DGS must be tested regularly DGS s are provided with a test button that may be activated to validate the alarm ...

Page 2: ...y to the Ackn Test button DC supply for external Strobe Horn Whether the DGS is powered by 24Vdc or 24Vac a 24Vdc power supply max 50mA is available between terminals 1 and 5 on connector x1 Jumpers JP4 open 19200 Baud JP4 closed 38400 Baud default JP5 open AO 0 20 mA JP5 closed AO 0 10 Volt default Note the DGS must be power cycled before any change to JP4 take effect Cable Gland opening Danfoss ...

Page 3: ...r general BMS system set the Modbus address using the DGS Service Tool using password 1234 when prompted See the DGS User Guide for details on operating the DGS Service Tool The Baud Rate is adjusted by jumper JP4 As default the setting is 38 4kBaud For integration with AK SM 720 350 change the setting to 19 2kBaud For more information about data communication see document RC8AC Sensor replacement...

Page 4: ... bottle with pressure regulator and a calibration adapter In doing so the set alarm thresholds are exceeded and all output functions are activated It is necessary to check if the connected output functions are working correctly e g the horn sounds the fan switches on devices shut down By pressing the push button on the horn the horn acknowledgment must be checked After removal of the reference gas...

Page 5: ...y 0 600 0 sec Alarm delay s When set to 1 the audible sounder are reset and the relays if defined Relay rest enable to no alarm indication When the alarm is reset or the time out duration is exceeded the value is reset to 0 Note The alarm condition is not reset only the output indication is reset 0 Alarm outputs not reset 1 Alarm outputs reset buzzer muted and relays reset if configured 0 1 0 Rese...

Page 6: ...on 0 32000 HFC 365 CO2 1825 R290 182 days 2 Days til calib Gas 2 Shows how many of Sensitivity remaining Note Value only updated after calibration 0 100 100 2 Rem sensivity Activates a mode which simulates an alarm Buzzer LED and relays all activate 1 Test function no alarm generation possible now Automatically falls back to Off after 15 min 0 back to Normal mode 0 1 0 Test Mode Analog Output Selc...

Page 7: ...l operation i e alarms are created and cleared 1 Alarms inhibited i e alarm status is not updated e g due to DGS in test mode 0 1 0 Alarm inhibited Critical Limit alarm 0 Alarm not active 1 Alarm gas limit exceeded and delay expired 0 1 0 2 Criti limit 0 OK 1 Fault Out of range under test Overrange or Underrange 0 1 0 2 Out of range 0 OK sensor no errors 1 Fault Sensor and Head failures 0 1 0 2 Wr...

Page 8: ... reached the end of life Carry out calibration routine or replace with a new factory calibrated sensor Yellow AO configured but not connected only 0 20 mA output Check wiring Sensor type does not match DGS specification Check gas type and measuring range Sensor may be disconnected from printed circuit board Check to see sensor is properly connected The sensor has been damaged and needs to be excha...

Reviews: