The assembly process for the “Connection kit - cable to cold lead + end termination (Pipeheat)” is
divided into four processes. The first process covers the assembly process of the ready-making of
the heating cable. The second process covers assembly process of the ready-making of the cold tail.
The third process covers assembly process between the ready-making of the heating cable and cold
tail. The fourth process covers assembly process of the “Sealing the end of the heating cable” for
protection of the end cap.
Ready-making of the heating cable
Drawing
Designation
Tools
30
- Outer Sheath removed
The outer sheath of the heating cable is
removed over a length of 30 mm.
Wire cutter,
knife and tape
measure
30
- Alu. foil removed
- Drain wires twisted
The aluminum foil screen and drain
wires are released and twisted, to be
used as the ground connection of the
cable.
Knife, and tape
measure
10
20
- Primary insulation removed
Remove 20 mm of the 30 mm insulation
jacket Check after cutting the insulation
cable that 10 mm is left.
Knife and tape
measure
20
10
- Conductor removed
Cut up the core material along one of the
two conductors and release and twist it. The
outermost of the 10 mm of the material is
removed from the other conductor.
Knife
The drain wires is twisted over
the heating cable
The drain wires is twisted over the
heating cable.
Installation Guide Connection kit - cable to cold lead + end termination (Pipeheat)