Display Installation
4
3 Display Installation
This section explains the steps necessary for proper lifting and installation of the display to
the sign structure.
Follow all guidelines and safety precautions in this manual when installing the display.
Do not modify the display or control system in any manner without the written permission
of Daktronics engineering staff. Any unauthorized modifications will void the warranty.
Display Installation Preparation
• Inspect the display for damage prior to installation
• Use all T-clips for mounting
• Provide an adequate support structure that is straight and level
•
Provide adequate ventilation that meets or exceeds display specifications listed on
the
Shop Drawing
• Use all T-clips for mounting using a continuous horizontal member
• Use all lift eyes when lifting the display
• Do not open the Galaxy
®
Large Matrix GS6 controller enclosure
• Do not block display ventilation system
• Do not use the lift eyes for display mounting
• Do not hang additional signage from Galaxy
®
Large Matrix GS6 series display.
Display Installation
1�
Use a utility knife to carefully cut away all of
the white packaging material from the display.
Be careful not to damage the face of the
display or LEDs.
Note:
If the display is multi-sectional, refer
before
continuing.
2�
Attach a crane or lift truck to the lift eyes on
the display's top.
Lift eye spacing is set at Daktronics and should
not be moved. Lift eyes should also remain in
place after installation is complete.
Ensure the angle between the top of the display and
the lifting strap is greater than 55°. Refer to
3�
Apply tension to the lift lines.
4�
Attach tag lines to the bracket. Refer to
.
5�
Unbolt the display from the shipping braces.
From Back
Tag Line
Tie Off
Angle must be
greater than 55°
Lift-Eye Bolts
Set Bolts
Figure 1:
Proper Display Lifting
Figure 2:
Tag Line Bracket