Installation Preparation
3
2 Installation Preparation
This section explains what to consider before installing a Daktronics Galaxy
®
eCCB
display.
Follow all guidelines and safety precautions in this manual when installing the display. Do
not modify the display or control system in any manner without the written permission of
Daktronics engineering staff.
Any unauthorized modifications will nullify the display warranty.
Pre-Installation Checklist
Verify the following before starting installation:
• The display was not damaged during shipping.
• The mounting structure will provide a straight and square mounting frame for the
display.
• The support structure can carry the weight of the display and meets local and
national codes.
•
Ensure proper power is available at sign structure – refer to shop drawing for display
power requirements.
• All display modules are fully latched into the display cabinet.
Structure Requirements
Support structure design depends on mounting method, installation height, display size,
and weight. Because every installation site is unique, Daktronics approves no single
procedure for mounting displays.
Things to consider prior to installation:
•
Display structure and mounting must not obstruct airflow - refer to shop drawing for
ventilation space requirements
• Self-tapping screws must be used for mounting to structure
• Light sensor must not be obstructed to maintain proper display dimming
For additional questions about display mounting requirements and specifications, refer
to the display shop drawing or contact Daktronics Technical Support at 800-DAKTRONICS
(800-325-8766).