Installation manual

5

VAM350~2000FC

Total Heat Exchanger

HRV (Heat Reclaim Ventilation)

4P415947-1A – 2017.08

System configuration

Independent system

Air conditioner linked operation system 

System

Standard method

Related items in 

Electric wiring

Independent system

• Up to 16 units can be controlled with the 

remote controller for HRV. (A system with 
two remote controls can be created in the 
master/slave switching.)

• All HRV operations can be used and 

indicated.

• Operation monitor output and humidifier 

operation are possible using Adapter 
PCB.

• Remote control cord should be procured 

locally.

 

(Maximum cord length: 500 m)

"When connecting to 

Remote controller for 

HRV" on page 16

Combined 

operation system 

with VRV systems 
and Sky-air series

1-group linked 

operation system

• A combined total of up to 16 air 

conditioners and the HRV can be 
controlled.

• The HRV ventilation mode can be 

operated independently when air 
conditioners are not being used.

• Using the local setting of the remote 

controller for air conditioners, various 
settings such as precool/pre-heat 
reservation on/off, ventilation flow rate, 
ventilation mode, etc.

"Standard 1-group 

linked-control 

system" on page 16

Multi-group 

(2 or more) linked 

operation system

• Since all VRV units are connected to a 

single line in view of installation, all VRV

 

units are subjects for operation.

• If there are problems operating all VRV

 

units, do not use this system.

"Linked control with 

more than two 

groups" on page 17

HRV

HRV

1

2

1

Remote controller 
for HRV

2

2-wire cord 
(produced locally)

VRV

HRV

1

2

1

Remote controller 
for air conditioner

2

Remote controller 
for air conditioner

VRV

VRV

VRV

VRV

HRV

HRV

1

2

5

5

5

5

3

4

6

1

Group 1

4

Group 4

2

Group 2

5

Remote controller 
for VRV

3

Group 3

6

Distant control 
adapter

NOTE

Adapter PCB for external input/output: BRP4A50A; Distant control adapter: KRP2A51 (installation box: KRP1B101).

Operation of two or more groups is not possible with direct duct connection.

With VAM types, the direct duct connection shown can also be selected for 1-group operation systems.

System

Standard method

Related items in 

Electric wiring

Direct duct connection system

• The HRV will operate only when the air 

conditioner fan is on.

• Other specifications are the same as 

those of the standard system.

"Direct duct 

connection system 

for 1-group operation 

system" on page 17

VRV

HRV

1

2

3

1

Remote controller 
for air conditioner

2

Remote controller 
for air conditioner

3

Duct

Summary of Contents for VAM350FC

Page 1: ...INSTALLATION MANUAL VAM350FC VAM500FC VAM650FC VAM800FC VAM1000FC VAM1500FC VAM2000FC Total Heat Exchanger HRV Heat Reclaim Ventilation Ceiling mounted duct type...

Page 2: ...50F 285 164 112 800 416 850 758 132 812 146 200 VAM500F 84 197 VAM650F 348 204 145 852 421 902 912 137 988 196 250 VAM800F 98 246 263 VAM1000F 1140 568 1190 VAM1500F 710 383 140 852 421 898 130 330 35...

Page 3: ...3 3 4 4...

Page 4: ...electrician and must comply with the applicable legislation Always use the air filter If the air filter is not used heat exchange elements will be clogged possibly causing poor performance and subseq...

Page 5: ...a domestic environment this product may cause radio interference in which case the user may be required to take adequate measures 1 Air suction discharge grille option 2 Inspection hole 450 mm field s...

Page 6: ...or bolt with washer and nut Before installation check for foreign objects such as vinyl and paper remaining inside the fan housing Attach the indoor SA RA and outdoor EA OA ducts by refering to the du...

Page 7: ...lation equipment inside the ceiling 7 Insulate the duct and the wall electrically when a metal duct is to be penetrated through the metal lattice and wire lattice or metal lining of a wooden structure...

Page 8: ...Standard 1 group linked control system on page 16 Multi group 2 or more linked operation system Since all VRV units are connected to a single line in view of installation all VRV units are subjects f...

Page 9: ...l device All individual control on page 18 Zone control system Use of the centralized controller enables zone control via the centralized control line maximum of 64 zones The central controller displa...

Page 10: ...ch the line outside the terminal board of the unit in accordance with electrical equipment standards The branch must be sheathed so as to provide a degree of insulation equal to or greater than the po...

Page 11: ...VAM350F VAM500F VAM650F VRV HRV P1 P1 P1 P2 P2 P2 L N 1 2 Out VRV HRV L N L N 1 1 2 2 P1 P2 F1 F1 T1 T1 P2 P1 F1 F2 J2 J3 JC L N J1 1 2 5 3 4 4 6 7 6 1 Outdoor unit BS unit 2 Switch box 3 Indoor unit...

Page 12: ...nd washer 5 Grounding terminal 6 Terminal board 7 Transmission wiring terminal board P1 P2 8 Transmission wiring to optional remote controller 9 Power supply cable 10 Wires for connection of additiona...

Page 13: ...ing any of these options on the VAM1500 2000 it is necessary to prepare the fixing plate EKMPVAM When installing KRP2A51 it is necessary to prepare the fixing box KRP1BA101 For VAM350 500 650 800 1000...

Page 14: ...edure and settings 1 Press the INSPECTION TRIAL button 1 for more than four seconds with the unit in the normal mode to enter the local setting mode 2 For BRC301B51 use the VENTILATION MODE button up...

Page 15: ...stallation manual 12 6 Press the PROGRAM CANCEL button 6 once to enter the settings The code display will stop blinking and light up 7 Press the INSPECTION TRIAL button 1 to return to normal mode SETT...

Page 16: ...C 21 C 22 C 23 C 24 C 25 C 26 C 27 C 28 C 29 C 30 C 8 Centralized zone interlock setting No Yes 9 Pre heat time extension setting 0min 30min 60min 90min 18 28 0 External signal JC J2 Last command Pri...

Page 17: ...in on Continuous operation Step1 Step2 Step3 Step4 Step5 Step6 Step7 Step8 2 SA fan step setting Step1 Step2 Step3 Step4 Step5 Step6 Step7 Step8 Step9 Step10 Step11 Step12 Step13 Step14 Step15 3 EA fa...

Page 18: ...sor of the unit automatically changes the ventilation of the unit in Bypass mode and Heat Exchange mode Heat Exchange mode In this mode the air passes through the heat exchanger element to effect Tota...

Page 19: ...nditioner to make the initial settings for the HRV units Refer to Initial setting under Item List of Settings on page 13 Pre cool pre heat function When the pre cool pre heat function is set the HRV u...

Page 20: ...n the remote controller for HRV is connected initial settings should be performed using the remote controller for HRV Set the same numbers as described above when using the remote controller for air c...

Page 21: ...minals This system allows connection of four on off controllers It is necessary to assign a central control group number to each HRV unit and air conditioner Regarding the setting of the group number...

Page 22: ...structions of the centralized controller The centralized controller can be used to control the individual units in the zone for ventilation operation Remote control Monitor of operation The operation...

Page 23: ...Example When measured 900 ppm in linear control the unit runs 20 minutes in H next 10 minutes in L and after elapse judges again Essential wiring Refer to Opening the switch box on page 8 and to the i...

Page 24: ...temperatures after the air conditioning operation stops for the night If the following conditions are satisfied the operation starts and when the indoor temperature reaches the air conditioning settin...

Page 25: ...ISTOR PTC S1C S2C LIMIT SWITCH DAMPER MOTOR X1M TERMINAL A1P X2M TERMINAL OUTSIDE INPUT A1P X3M TERMINAL POWER SUPPLY V1R DIODE Z1F NOISE FILTER REMOTE CONTROLLER SS1 SELECTOR SWITCH OPTIONAL ACCESSOR...

Page 26: ......

Page 27: ......

Page 28: ......

Page 29: ...4P415947 1A 2017 08 Copyright 2015 Daikin...

Reviews: