IM 926-3 • ROOFPAK APPLIED SYSTEMS 36 www.DaikinApplied.com
Mechanical Installation
Phase III. Reconnecting power and control wiring
The wire harnesses are coiled in the condenser section base
). The power wires into the lower base rail
raceway and the control wires into the upper raceway.
1.
Uncoil the harnesses and feed them through the base
rail of the air handler section and make the proper
connections. The power wires terminate to the load side
of the contactors; the control wires plug into the plug
patch panel.
2. The liquid line solenoid valve harness is split into two
harnesses. Install one half in the plug patch panel in the
).
3.
The other half of the harness is located in conduit on the
bulkhead of the air handler section (see
4.
Terminate the conduit to the vertical raceway in the
condenser section (see
5.
Wire nut the ends of the two harnesses together.
6.
The optional hot gas bypass solenoid valve harness
is coiled in the upper raceway of the condenser base
). Route the plug end of the harness
through the air handler raceway and into the main control
cabinet and plug into the plug patch panel.
Figure 54: Connecting Power/Control Wiring (015C - 040C)
Figure 55: Remove Vertical Raceway
Unit A
ir F
low
Summary of Contents for RoofPak RPS Series
Page 129: ......