Si241319
Procedure to Remove Compressor
Removal Procedure
5
4. Procedure to Remove Compressor
Procedure
Warning
Be sure to wait for 10 minutes or more after turning off all power
supplies before disassembling work.
Step
Procedure
Points
Removing top panel and
front panel according to
the “Procedure to
Remove Outside Panels”.
Check that the refrigerant is
completely discharged
before starting the
disassembling work.
Color of terminal end
R18 • 24NUV2S
1 of compressor fixing nuts
is outside of the partition
plate.
1
To remove the terminal
cover, press the
protruded section on
both right and left sides.
2
Disconnect the lead
wires from the
terminals.
3
Dismount the 3 nuts
fixing the compressor.
4
Disconnect 3 brazed
joints.
5
Lift and take out the
compressor.
Compressor
fixing nut
Stop valve
mounting plate
Brazed joints
(3 joints)
(S)
YLW
(C)
BLU
(R)
RED