3. PREPARATION BEFORE INSTALLATION
(1)
Check the relation of location between the ceiling
opening and the indoor unit hanging bolts.
1
Decoration panel
4
Hanging bolt pitch
3
Indoor unit
2
Ceiling opening
1
Decoration panel
2
Ceiling opening
3
Indoor unit
5
Hanging bolt pitch
Refrigerant
piping
Hanging
bolt (×4)
A
Fig. 4
[unit: in. (mm)]
1
37-3/8 (950)
2
33-7/8 – 35-7/8 (860 – 910)
3
33-1/16 (840)
4
30-3/4 (780)
5
28 (710)
Ceiling
View as seen from
A
Hanger
Fig. 5
Decoration Panel
BYCQ125B-W1
BYCQ125BGW1
in. (mm)
4-15/16 – 5-1/8
(125 – 130)
8-1/16 – 8-1/4
(205 – 210)
CAUTION
Reduce the distance between the unit and ceiling to
1-3/8 in. (35 mm) or below in order to maintain an over-
lapping panel margin 13/16 in. (20 mm) for the opening
on the ceiling. If the distance exceeds 1-3/8 in. (35 mm),
attach ceiling material to the part marked
or replace
the ceiling.
(Refer to Fig. 6)
Frame
≤
1-3/8 (35)
≤
1-3/8 (35)
33-7/8 to 35-7/8 (860 – 910)
(Ceiling-panel
overlapping
dimension)
Ceiling
material
(Ceiling-opening dimension)
≥
13/16
(20)
≥
13/16
(20)
[unit: in. (mm)]
Fig. 6
(2)
Make the ceiling opening required for installation.
•
Use the installation pattern paper (5) matched to the
ceiling opening dimension.
•
Make the ceiling opening required for installation at
the installation location and carry out refrigerant/drain
piping, power supply wiring, remote controller wiring
(not needed in case of wireless remote con troller) and
wiring between the indoor and outdoor units. (Refer
to each section
5. REFRIGERANT PIP ING WORK,
6. DRAIN PIPING WORK
and
7. ELECTRIC WIRING
WORK
)
•
After making the opening, sometimes it is necessary
to reinforce the ceiling framework to maintain a level
ceiling and prevent it from vibrating.
For details, consult with the builder and interior de-
signer.
(3) Install the hanging bolts.
•
Use M8 or M10 bolts for hanging the indoor unit.
•
Use hole-in-anchors for the existing bolts and embed
-
ded inserts or foundation bolts for new bolts, and fix the
indoor unit firmly to the building so that it may withstand
the mass of the unit.
In addition, adjust clearance (2 – 4 in. (50 – 100 mm))
from the ceiling in advance.
<Installation examples>
2 – 4 in.
(50 – 100 mm)
Foundation bolt
Hanging bolt
Ceiling slab
Long nut or turn-buckle
Ceiling surface
Note) The above shown parts are all field supply.
4.
INSTALLATION OF INDOOR UNIT
<<It is easy to attach the optional parts (except for deco-
ration panel) before installing the indoor unit. Refer to
also the installation manual attached to the optional
parts.>>
For installation, use the attached installation parts and
specified parts.
[Install the indoor unit in the order of steps (1), (2), (3), (4), (5),
and (6) in case of a newly built ceiling, or in the order of steps
(1), (3), (4), and (5) in case of an existing ceiling.]