background image

10 Commissioning

Installation manual

10

FTXTA30B2V1B(W)(B)

Daikin room air conditioner

3P482320-12U – 2021.03

10

Commissioning

NOTICE

General 

commissioning 

checklist.

 

Next 

to 

the

commissioning  instructions  in  this  chapter,  a  general
commissioning  checklist  is  also  available  on  the  Daikin
Business Portal (authentication required).

The  general  commissioning  checklist  is  complementary  to
the  instructions  in  this  chapter  and  can  be  used  as  a
guideline and reporting template during the commissioning
and hand-over to the user.

NOTICE

ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.

10.1

Checklist before commissioning

After  the  installation  of  the  unit,  first  check  the  items  listed  below.
Once all checks are fulfilled, the unit must be closed. Power-up the
unit after it is closed.

You  read  the  complete  installation  instructions,  as
described in the 

installer reference guide

.

The 

indoor units

 are properly mounted.

The 

outdoor unit

 is properly mounted.

Air inlet/outlet

Check  that  the  air  inlet  and  outlet  of  the  unit  is  NOT
obstructed  by  paper  sheets,  cardboard,  or  any  other
material.

There are NO 

missing phases

 or 

reversed phases

.

The 

refrigerant  pipes

  (gas  and  liquid)  are  thermally

insulated.

Drainage

Make sure drainage flows smoothly.

Possible consequence: 

Condensate water might drip.

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

fuses

  or  locally  installed  protection  devices  are

installed according to this document, and have NOT been
bypassed.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

The  specified  wires  are  used  for  the 

interconnection

cable

.

The indoor unit receives the signals of the 

user interface

.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

The 

insulation resistance

 of the compressor is OK.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

There are NO 

refrigerant leaks

.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

The 

stop valves

 (gas and liquid) on the outdoor unit are

fully open.

10.2

To perform a test run

Prerequisite: 

Power supply MUST be in the specified range.

Prerequisite: 

Test  run  may  be  performed  in  cooling  or  heating

mode.

Prerequisite: 

Test run should be performed in accordance with the

operation  manual  of  the  indoor  unit  to  make  sure  that  all  functions
and parts are working properly.

1

In  cooling  mode,  select  the  lowest  programmable  temperature.
In heating mode, select the highest programmable temperature.
Test run can be disabled if necessary.

2

When  the  test  run  is  finished,  set  the  temperature  to  a  normal
level. In cooling mode: 26~28°C, in heating mode: 20~24°C.

3

The  system  stops  operating  3  minutes  after  the  unit  is  turned
OFF.

10.2.1

To perform a test run using the user
interface

1

Press 

 to switch the system on.

2

Press 

 and 

 simultaneously.

3

Press 

, select 

and press 

.

Result: 

Test  run  operation  will  stop  automatically  after  about

30 minutes.

4

To stop operation sooner, press 

.

11

Disposal

NOTICE

Do  NOT  try  to  dismantle  the  system  yourself:  dismantling
of  the  system,  treatment  of  the  refrigerant,  oil  and  other
parts  MUST  comply  with  applicable  legislation.  Units
MUST  be  treated  at  a  specialised  treatment  facility  for
reuse, recycling and recovery.

12

Technical data

▪ A 

subset

  of  the  latest  technical  data  is  available  on  the  regional

Daikin website (publicly accessible).

▪ The 

full  set

  of  latest  technical  data  is  available  on  the  Daikin

Business Portal (authentication required).

12.1

Wiring diagram

The wiring diagram is delivered with the unit, located inside of
the outdoor unit (bottom side of the top plate).

12.1.1

Unified wiring diagram legend

For applied parts and numbering, refer to the wiring diagram on the
unit.  Part  numbering  is  by  Arabic  numbers  in  ascending  order  for
each part and is represented in the overview below by "*" in the part
code.

Symbol

Meaning

Symbol Meaning

Circuit breaker

Protective earth

Connection

Protective earth (screw)

Summary of Contents for FTXTA30B2V1BB

Page 1: ...Installation manual Daikin room air conditioner English Installation manual Daikin room air conditioner FTXTA30B2V1BW FTXTA30B2V1BB ...

Page 2: ...cal data 10 12 1 Wiring diagram 10 12 1 1 Unified wiring diagram legend 10 1 About the documentation 1 1 About this document INFORMATION Make sure that the user has the printed documentation and ask him her to keep it for future reference Target audience Authorised installers INFORMATION This appliance is intended to be used by expert or trained users in shops in light industry and on farms or for...

Page 3: ... site and all electrical construction MUST comply with the applicable legislation WARNING If the power supply has a missing or wrong N phase equipment might break down Establish proper earthing Do NOT earth the unit to a utility pipe surge absorber or telephone earth Incomplete earthing may cause electrical shock Install the required fuses or circuit breakers Secure the electrical wiring with cabl...

Page 4: ...edical equipment E g persons using cardiac pacemakers or defibrillators This product may cause electromagnetic interference Auto control equipment E g automatic doors or fire alarm equipment This product may cause faulty behaviour of the equipment Microwave oven It may affect wireless LAN communications 4 2 2 Basic parameters Parameter Value Frequency range 2400 MHz 2483 5 MHz Radio protocol IEEE ...

Page 5: ... a a a a h 610 605 555 k j i a Recommended mounting plate fixing spots g Value for tape measure b Pocket for the pipe port cover h Position for tape measure at symbol c Use tape measure as shown i Drain hose d Tabs for placing a spirit level j Liquid pipe e Unit center k Gas pipe f Hole for embedded piping Ø65 mm 5 2 2 To drill a wall hole CAUTION For walls containing a metal frame or a metal boar...

Page 6: ...eft side left back or left bottom INFORMATION The factory default is right side piping For left side piping remove the piping from the right side and install it on the left side 1 Remove the insulation fixing screw on the right side and remove the drain hose 2 Remove the drain plug on the left side and attach it to the right side NOTICE Do NOT apply lubricating oil refrigerant oil to the drain plu...

Page 7: ... the refrigerant piping DANGER RISK OF BURNING SCALDING 6 2 1 To connect the refrigerant piping to the indoor unit WARNING MILDLY FLAMMABLE MATERIAL The refrigerant inside this unit is mildly flammable Pipe length Keep refrigerant piping as short as possible 1 Connect refrigerant piping to the unit using flare connections 2 Insulate the refrigerant piping interconnection cable and drain hose on th...

Page 8: ...make contact with electrical parts can cause malfunctions smoke or fire a b c a Terminal block b Electrical component block c Cable clamp 5 Strip the wire ends approximately 15 mm 6 Match wire colours with terminal numbers on the indoor unit terminal blocks and firmly screw the wires to the corresponding terminals 7 Connect the earth wire to the corresponding terminal 8 Firmly fix the wires with t...

Page 9: ...tom edge of the indoor unit with both hands until it is firmly caught by the mounting plate hooks 4 Secure the indoor unit to the mounting plate using 2 indoor unit fixing screws M4 12L accessory 9 Configuration 9 1 To set a different address In case 2 indoor units are installed in 1 room different addresses for 2 user interfaces can be set 1 Remove the cover and the batteries from the user interf...

Page 10: ...nts or squeezed pipes on the inside of the indoor and outdoor units There are NO refrigerant leaks The correct pipe size is installed and the pipes are properly insulated The stop valves gas and liquid on the outdoor unit are fully open 10 2 To perform a test run Prerequisite Power supply MUST be in the specified range Prerequisite Test run may be performed in cooling or heating mode Prerequisite ...

Page 11: ...K M Magnetic relay L Live L Coil L R Reactor M Stepper motor M C Compressor motor M F Fan motor M P Drain pump motor M S Swing motor MR MRCW MRM MRN Magnetic relay N Neutral n N Number of passes through ferrite core PAM Pulse amplitude modulation PCB Printed circuit board Symbol Meaning PM Power module PS Switching power supply PTC PTC thermistor Q Insulated gate bipolar transistor IGBT Q C Circui...

Page 12: ...3P482320 12U 2021 03 Copyright 2021 Daikin Verantwortung für Energie und Umwelt ...

Reviews: