Pump Down Operation
SiUS091628EA
113
Trial Operation and Field Settings
1. Pump Down Operation
Outline
In order to protect the environment, be sure to conduct pump down operation when relocating or
disposing of the unit.
Details
1. Remove the valve caps from the liquid stop valve and the gas stop valve.
2. Carry out forced cooling operation.
3. After 5 to 10 minutes, close the liquid stop valve with a hexagonal wrench.
4. After 2 to 3 minutes, close the gas stop valve and stop the forced cooling operation.
Refer to Forced Cooling Operation on page 114 for details.
Gas stop valve
Valve cap
Close
Liquid stop valve
Service port
(R13628)
Hexagonal
wrench
Summary of Contents for FFQ09Q2VJUFFQ12Q2VJUFFQ15Q2VJUFFQ18Q2VJURX09QMVJURX12QMVJURX15QMVJURX18QMVJU
Page 12: ...SiUS091628EA 1 List of Functions Part 1 List of Functions 1 Functions 2...
Page 14: ...SiUS091628EA 3 Specifications Part 2 Specifications 1 Specifications 4...
Page 120: ...Check SiUS091628EA 109 Service Diagnosis 15 18 class R20701 1 2 3 4 Multimeter...
Page 122: ...Check SiUS091628EA 111 Service Diagnosis 15 18 class R20704 W V U DC_P1 DC_N1...