19
Ducted Air Conditioners
Installation Manual
TEST OPERATION
when using BRC1E62 remote control.
(
Please use zone controller installation instructions).
Refer to the selection of “FOR THE FOLLOWING ITEMS, TAKE SPECIAL CARE DURING CONSTRUCTION
AND CHECK AFTER INSTALLATION IS FINISHED”.
Also see installation manual supplied with the outdoor unit.
•
Check that wiring work of the indoor unit and the outdoor unit is completed.
•
Check that EL. COMPO. BOX cover of the indoor unit and the outdoor unit is closed.
•
After refrigerant piping, drain piping and electric wiring are completed, clean inside of the indoor unit and
decorative panel.
•
Perform the test operation according to following procedure.
-1
Make sure to turn on the power supply
more than 6 hours before operation
start with front panel closed to protect
compressor.
-2
Confirm that stop valves of both liquid
and gas are opened.
<Make sure that outer panel and
piping cover are closed before
operation (danger of electric
shock).>
*
After air purge by vacuum pump,
refrigerant pressure may not rise
even though the stop valve is
opened. The reason is that refrigerant
system of the outdoor unit is blocked
by electrical expansion valve or the
like. Operation is no problem.
-3
Set the operation mode to cooling by
using the remote controller.
-4
Press and hold Cancel button for
4 seconds or longer. Field setting
menu is displayed.
-5
Select
Test Operation
in the Service
Settings menu, and press Menu/Enter
button. Basic screen returns and “Test
Operation” is displayed.