Program the field supplied controller to generate a 0–10 V signal
within conditions as listed. Also refer to the graphic and further data
in this paragraph for more details.

When target temperature is reached: 5 V

When more capacity is needed: 5–10 V

When less capacity is needed: 0–5 V

Operation with fixed T

e

 temperature control

The evaporating temperature (

T

e

) at which the application has to

operate can be set by code numbers as listed below.

Operation setting in case of power failure

O

PERATION

 

AND

 

DISPLAY

 

SIGNALS

T

ROUBLESHOOTING

To  set up the system and make trouble shooting possible, it is
required to connect the remote controller to the option kit.

Not a malfunction of the air conditioner

The system does not operate

The system does not restart immediately after the cooling is
requested.
If the operation lamp lights, the system is in normal operating
condition.
It does not restart immediately because one of its safety devices
actuates to prevent the system from being overloaded. The
system will turn on again automatically after 3 minutes.

The system does not restart immediately after the power supply
is turned on.
Wait 1 minute until the micro computer is prepared for operation.

Trouble shooting

If one of the following malfunctions occurs, take the measures shown
below and contact your dealer.

The system must be repaired by a qualified service person.

If a safety device such as a fuse, a breaker, or an earth leakage
breaker frequently actuates, or ON/OFF switch does not
properly work.
Turn off the main power switch.

If the display 

, the unit number and the operation lamp

flash and the malfunction code appears;
Notify your dealer and report the malfunction code.

If the system does not operate properly, and none of the above
mentioned malfunctions is evident, investigate the system according
to the following procedures.

A

Controller voltage output to EKEXFCB

Capacity increase area

Capacity decrease area

Voltage output  = linear function with 

T

T

 = [actual measured temperature] – [target temperature]

When 

T=0, the target temperature is reached.

T

max

 = maximum temperature variation as defined by installation

Recommended value for 

T

max

=[1°C~5°C].

T (°C)

T

max

0

+

T

max

Voltage output from controller 
(field supply)

0 V

5 V

10 V

Mode No.

Code No.

Description of setting

(*)

(*)

Depending on the operating temperature condition or on selection of the 
evaporating unit, operation or safety activation of the outdoor unit may take 
priority and actual T

e

 will be different from the set T

e

 .

13(23)–1

01

T

e

 = 3°C

02

T

e

 = 4°C

03

T

e

 = 5°C

04

T

e

 = 6°C (factory setting)

05

T

e

 = 7°C

06

T

e

 = 8°C

07

T

e

 = 9°C

08

T

e

 = 10°C

Measures must be taken to ensure that after power failure,
the T1/T2 operation signal is according to the setting of
your preference. Neglecting this caution will result in
improper operation.

Mode No.

Code No.

Description of setting

12(22)–5

01

The T1/T2 operation signal contact 
must be open at power restore.

(*)

(*)

After power failure, the T1/T2 operation signal contact must be changed to open 
(no cooling requested).

02

After power failure, the status of the 
T1/T2 operation signal contact 
(operation request) must remain 
identical to the initial T1/T2 contact 
status prior to the power failure.

0

Tmax

+

Tmax

T=0

5

10 V

°C

A

Output

C1/C2 error 

signal

Error: open

Abnormal operation on 
condenser or control system

Power failure

No error: closed 

(relay activated)

Normal operation

T1/T2 is open: no error 
detection anymore

C3/C4 operation 

signal

Open

Compressor not operating

Closed

Compressor operating

Input

C5/C6: capacity 

step

0–10 V

Only necessary for field 
setting 13(23)–0 = 01
0–10 V capacity control

(*)

(*)

Refer to paragraph 

"Operation with 0–10 V capacity control" on page 8

.

T1/T2 operation 

input

(†)

(†) See field setting 12(22)–5.

Open

No cooling requested

Closed

Cooling requested

The fan of the evaporator must operate before cooling
operation is required to the outdoor unit.

When the operation signal is activated, the evaporator
and fan must operate. Failure to this will cause a
safety to operate or freezing up of the evaporator (air
handling unit).

Summary of Contents for EKEXFCBAV3

Page 1: ...INSTALLATION AND OPERATION MANUAL EKEXFCBAV3 EKEXDCBAV3 Option kit for combination of Daikin condensing units with field supplied evaporators...

Page 2: ...Y1 expansion valve gas liquid N L P1 P2 C5 C6 0 10 V remocon outdoor F2 F1 F1 F2 T1 T2 ON OFF error C1 C2 operation C3 C4 0 10 3 4 6 5 R3T R2T 8 9 3 7 5 6 1 X24A 2 4 3 4 5 1 2 10 1 5 6 3 10 13 11 7 9...

Page 3: ...normalizacyjnych pod warunkiem e u ywane s zgodnie z naszymi instrukcjami 18 sunt n conformitate cu urm torul urm toarele standard e sau alt e document e normativ e cu condi ia ca acestea s fie utili...

Page 4: ...t to control the room temperature This system does not require a specific external controller INSTALLATION ACCESSORIES Obligatory accessory Refer to chapter Valve kit installation on page 3 for instal...

Page 5: ...oxes and may reduce its lifetime and influence its operation Choose a flat and strong mounting surface Parts and components 1 Outdoor unit 2 Control box EKEXFCB EKEXDCB 3 Air handling unit field suppl...

Page 6: ...not braze yet 4 Remove the pipe fixing clamp C by unscrewing 2x M5 5 Remove the upper and lower pipe insulations 6 Braze the field piping 7 After brazing put the lower pipe insulation back in place a...

Page 7: ...l wiring refer to paragraph Electric wiring work on page 4 4 Install the screw nuts 5 Close the unnecessary openings with stoppers closing cups 6 Close the lid securely after installation to ensure th...

Page 8: ...lve X1M R1 R2 Thermistor liquid X1M R3 R4 Thermistor gas X1M Y1 6 Expansion valve X2M P1 P2 Communication remote controller X2M C1 C2 Output error status X2M C3 C4 Output operation compressor ON OFF X...

Page 9: ...e X1M P1 P2 Communication remote controller X1M T1 T2 Input ON OFF X1M F1 F2 Communication outdoor unit Field wiring L Live N Neutral Connector Wire clamp Protective earth screw Separate component Opt...

Page 10: ...stor cable or loosening of the thermistor may result in bad contact and incorrect temperature measurement Fixation of the thermistor 1 Fix the thermistor with insulating aluminum tape field supply in...

Page 11: ...Field settings for EKEXDCB Refer to the installation manuals of both the outdoor unit and the remote controller Field settings for EKEXFCB When changing the settings 1 Make the required settings 2 Tu...

Page 12: ...g procedures A Controller voltage output to EKEXFCB Capacity increase area Capacity decrease area Voltage output linear function with T T actual measured temperature target temperature When T 0 the ta...

Page 13: ...alified service person to clean the air filter Check if the doors or the windows are open Shut doors or windows to prevent wind from coming in Check if direct sunlight enters the room Use curtains or...

Page 14: ...Zandvoordestraat 300 B 8400 Oostende Belgium 4PW30903 1...

Reviews: