background image

6 Piping installation

Installation manual

11

ATXF20~42E5V1B
Daikin room air conditioner
3P650253-11H – 2022.10

Refrigerant piping material

Piping material:

 phosphoric acid deoxidised seamless copper

Flare connections:

 Only use annealed material.

Piping temper grade and thickness:

Outer diameter

(Ø)

Temper grade

Thickness (t)

(a)

6.4 mm (1/4")

Annealed (O)

≥0.8 mm

t

Ø

9.5 mm (3/8")

12.7 mm (1/2")

(a)

Depending on the applicable legislation and the maximum
working pressure of the unit (see "PS High" on the unit name
plate), larger piping thickness might be required.

6.1.2

Refrigerant piping insulation

▪ Use polyethylene foam as insulation material:

▪ with a heat transfer rate between 0.041 and 0.052 W/mK (0.035

and 0.045 kcal/mh°C)

▪ with a heat resistance of at least 120°C

▪ Insulation thickness

Pipe outer diameter

p

)

Insulation inner

diameter (Ø

i

)

Insulation thickness

(t)

6.4 mm (1/4")

8~10 mm

≥10 mm

9.5 mm (3/8")

12~15 mm

≥13 mm

12.7 mm (1/2")

14~16 mm

≥13 mm

Ø

i

Ø

i

t

Ø

p

Ø

p

If  the  temperature  is  higher  than  30°C  and  the  humidity  is  higher
than RH 80%, the thickness of the insulation materials should be at
least  20  mm  to  prevent  condensation  on  the  surface  of  the
insulation.

6.2

Connecting the refrigerant piping

DANGER: RISK OF BURNING/SCALDING

6.2.1

Guidelines when connecting the
refrigerant piping

Take the following guidelines into account when connecting pipes:

▪ Coat  the  flare  inner  surface  with  ether  oil  or  ester  oil  when

connecting  a  flare  nut.  Tighten  3  or  4  turns  by  hand,  before
tightening firmly.

▪ ALWAYS use 2 wrenches together when loosening a flare nut.

▪ ALWAYS use a spanner and torque wrench together to tighten the

flare nut when connecting the piping. This to prevent nut cracking
and leaks.

a

b

c

d

a

Torque wrench

b

Spanner

c

Piping union

d

Flare nut

Piping size

(mm)

Tightening

torque (N•m)

Flare

dimensions (A)

(mm)

Flare shape

(mm)

Ø6.4

15~17

8.7~9.1

R=

0.4~0.8

±2

45°

90°

±2

ØA

Ø9.5

33~39

12.8~13.2

6.2.2

To connect the refrigerant piping to the
indoor unit

WARNING: MILDLY FLAMMABLE MATERIAL

The refrigerant inside this unit is mildly flammable.

Pipe length

. Keep refrigerant piping as short as possible.

1

Connect refrigerant piping to the unit using 

flare connections

.

2

Insulate 

the  refrigerant  piping,  interconnection  cable  and  drain

hose on the indoor unit as follows:

c

a

b

f

d

g

e

a

Gas pipe

b

Gas pipe insulation

c

Interconnection cable

d

Liquid pipe

e

Liquid pipe insulation

f

Finishing tape

g

Drain hose

NOTICE

Make  sure  to  insulate  all  refrigerant  piping.  Any  exposed
piping might cause condensation.

6.3

Checking the refrigerant piping

6.3.1

To check for leaks

NOTICE

Do NOT exceed the unit's maximum working pressure (see
"PS High" on the unit name plate).

NOTICE

ALWAYS  use  a  recommended  bubble  test  solution  from
your wholesaler.

NEVER use soap water:

▪ Soap  water  may  cause  cracking  of  components,  such

as flare nuts or stop valve caps.

▪ Soap  water  may  contain  salt,  which  absorbs  moisture

that will freeze when the piping gets cold.

▪ Soap  water  contains  ammonia  which  may  lead  to

corrosion  of  flared  joints  (between  the  brass  flare  nut
and the copper flare).

1

Charge the system with nitrogen gas up to a gauge pressure of
at  least  200  kPa  (2  bar).  It  is  recommended  to  pressurize  to
3000 kPa (30 bar) in order to detect small leaks.

2

Check  for  leaks  by  applying  the  bubble  test  solution  to  all
connections.

Summary of Contents for ATXF20E5V1B

Page 1: ...Installation manual Daikin room air conditioner English Installation manual Daikin room air conditioner ATXF20E5V1B ATXF25E5V1B ATXF35E5V1B ATXF42E5V1B...

Page 2: ...miniai bus eksploatuojami laikantis m s instrukcij atbilst d m direkt v m vai regul m ja vien ie izstr d jumi tiek lietoti saska ar m su instrukcij m s v zhode s nasleduj cou imi smernicou ami alebo p...

Page 3: ...are used in accordance with our instructions as amended S I 2016 1101 Electrical Equipment Safety Regulations 2016 S I 2016 1091 Electromagnetic Compatibility Regulations 2016 S I 2008 1597 Supply of...

Page 4: ...run 15 10 2 1 To perform a test run in winter season 15 11 Disposal 15 12 Technical data 16 12 1 Wiring diagram 16 12 1 1 Unified wiring diagram legend 16 1 About the documentation 1 1 About this docu...

Page 5: ...sucked in This will cause abnormal pressure in the refrigeration cycle which may result in equipment damage and even injury CAUTION Incomplete flaring may cause refrigerant gas leakage Do NOT re use f...

Page 6: ...them with bare hands DANGER RISK OF ELECTROCUTION Disconnect the power supply for more than 10 minutes and measure the voltage at the terminals of main circuit capacitors or electrical components befo...

Page 7: ...n and with applicable legislation and are executed ONLY by authorised persons 5 1 1 Installation site requirements of the indoor unit INFORMATION The sound pressure level is less than 70 dBA Air flow...

Page 8: ...and firmly engage the 3 upper hooks 2 Install 2 screws back on the front grille 3 Install the air filter and then mount the front panel 5 2 5 To remove the electrical wiring box cover 1 Remove the fr...

Page 9: ...t cover INFORMATION To connect the piping on right side right bottom left side or left bottom the pipe port cover MUST be removed 1 Cut off the pipe port cover from inside the front grille using a cop...

Page 10: ...t side and install it on the left side 1 Remove the insulation fixing screw on the right side and remove the drain hose 2 Remove the drain plug on the left side and attach it to the right side NOTICE...

Page 11: ...e a spanner and torque wrench together to tighten the flare nut when connecting the piping This to prevent nut cracking and leaks a b c d a Torque wrench b Spanner c Piping union d Flare nut Piping si...

Page 12: ...thout thermal insulation as such pipes will be very hot 7 1 Specifications of standard wiring components NOTICE We recommend using solid single core wires If stranded wires are used twist the conducto...

Page 13: ...rap refrigerant piping interconnection cable and drain hose together using insulation tape Overlap at least half the width of the tape with each turn d e c b f a 2 a Drain hose b Interconnection cable...

Page 14: ...he operation lamp was blinking repeat the setting process from the beginning 9 When the setting is complete press Model Button FTXF ATXF Result The user interface will return to the previous screen 10...

Page 15: ...ary 2 When the test run is finished set the temperature to a normal level In cooling mode 26 28 C in heating mode 20 24 C 3 The system stops operating 3 minutes after the unit is turned OFF 10 2 1 To...

Page 16: ...Meaning A P Printed circuit board BS Pushbutton ON OFF operation switch BZ H O Buzzer C Capacitor AC CN E HA HE HL HN HR MR _A MR _B S U V W X A K R_ NE Connection connector D V D Diode DB Diode brid...

Page 17: ...3P650253 11H 2022 10 Symbol Meaning V R Diode bridge Insulated gate bipolar transistor IGBT power module WRC Wireless remote controller X Terminal X M Terminal strip block Y E Electronic expansion va...

Page 18: ......

Page 19: ......

Page 20: ...ANBUL T RK YE Tel 0216 453 27 00 Faks 0216 671 06 00 a r Merkezi 444 999 0 Web www daikin com tr G lsuyu Mahallesi Fevzi akmak Caddesi Bur ak Sokak No 20 34848 Maltepe 3P650253 11H 2022 10 Copyright 2...

Reviews: