7.3 Mounting the outdoor unit
7.3.1 About mounting the outdoor unit
When
You have to mount the outdoor unit before you can connect the water piping.
Typical workflow
Mounting the outdoor unit typically consists of the following stages:
1
Providing the installation structure.
2
Installing the outdoor unit.
3
Providing drainage.
4
Preventing the unit from falling over.
5
Protecting the unit against snow and wind by installing a snow cover and baffle
plates. See "Preparing installation site" in
7.3.2 Precautions when mounting the outdoor unit
INFORMATION
Also read the precautions and requirements in the following chapters:
▪
General safety precautions
▪
Preparation
7.3.3 To provide the installation structure
Check the strength and level of the installation ground so that the unit will not
cause any operating vibration or noise.
Fix the unit securely by means of foundation bolts in accordance with the
foundation drawing.
Prepare 6 sets of anchor bolts, nuts and washers (field supply) as follows:
620
350
(345-355)
a
(mm)
261.5
>150
6× M12
a
Make sure not to cover the drain holes.
In any case, make sure the unit is positioned at least 100 mm above the maximum
expected level of snow.