Trial Operation and Testing

• Before starting the test run, measure the voltage at the primary side of the safety breaker. Check that it is 220-240V.
• Check that all liquid and gas stop valves are fully open.
• Check that piping and wiring all match. The wiring error check can be conveniently used for underground wiring and other wiring 

that cannot be directly checked.

1.

Wiring error check

• This product is capable of automatic correction of wiring error.
• Press the “wiring error check switch” on the outdoor unit service monitor 

print board. However, the wiring error check switch will not function for 
one minute after the safety breaker is turned on, or depending on the 
outside air conditions (See NOTE 2.). Approximately 10–15 minutes 
after the switch is pressed, the errors in the connection wiring will be 
corrected.

If self-correction is not possible, check the indoor unit wiring and piping 
in the usual manner.

NOTE:

1) For two rooms, LED 3 and 4 are not displayed, and for three rooms, LED 4 is not displayed.
2) If the outside air temperature is  

5

°

C or less

 , the wiring error check function will not operate.

3) After wiring error check operation is completed, LED indication will continue until ordinary operation starts. 

This is normal.

4) Follow the product diagnosis procedures. (Check the nameplate on the underside of the stop valve.)

Wiring error 
check switch 
(SW3)

Service PC-board

The service monitor LEDs indicate whether or not correction is
possible, as shown in the table below. For details about how to read the 
LED display, refer to the service guide.

LED

Status

1

2

3

4

All

   Flashing

Automatic correction impossible

Automatic correction completed

Abnormal stop [NOTE. 4]

Message

Flashing   

One after another

(One or more of LEDs 1 to 4 are ON)

Terminal block

Wiring error check

LED lighting sequence after a wiring correction.

Order of LED flashing: 2 

 1 

 3 

 4

From Room C 
to the “kitchen”

From Room B 

to the “living room”

From Room D 

to the “children’s room”

From Room A 

to the “bedroom”

Wiring correct example 

 The figure at left shows branch wiring.

01_EN_3P164392-4P.fm  Page 15  Tuesday, October 30, 2012  11:08 AM

Summary of Contents for 3MXS40K2V1B

Page 1: ...Nederlands Espa ol Italiano Portugues English T rk e Installation manual R410A Split series Montaj k lavuzlar R410A Split serisi Installationsanleitung Split Baureihe R410A Manuel d installation S ri...

Page 2: ...TRIES LTD Low Voltage 2006 95 EC Electromagnetic Compatibility 2004 108 EC 3SB64564 17J 3MXS40K2V1B Shinri Sada Manager Quality Control Department DAIKIN TCF 015 N20 09 2011 DEKRA Certification B V NB...

Page 3: ...2004 108 EC 3SB64564 1 Shinri Sada Manager Quality Control Department 1st of Dec 2008 DAIKIN TCF 015 K1 07 2007 2MXS52E2V1B 2AMX52E2V1B 3MXS52E2V1B 3AMX52E2V1B 3MKS50E2V1B 4MKS58E2V1B 2MXS52E3V1B 2AMX...

Page 4: ...3MXS40K2V1B 2MXS52E2V1B 2AMX52E2V1B 3MXS52E2V1B 3AMX52E2V1B 3MKS50E2V1B 4MKS58E2V1B 2MXS52E3V1B 2AMX52E3V1B 3MXS52E3V1B 3AMX52E3V1B 3MKS50E3V1B 4MKS58E3V1B 3SB65451 5A Shinri Sada Manager Quality Cont...

Page 5: ...TCF 015 P6 07 2012 DEKRA Certification B V NB0344 74736 KRQ EMC97 4957 3SB65451 9D Shinri Sada Manager Quality Control Department 3MXS40K3V1B 3MXS52E4V1B 3AMX52E4V1B Machinery 2006 42 EC Electromagne...

Page 6: ...3SB65451 4 fm Page 2 Thursday October 27 2011 4 49 PM...

Page 7: ...ls If refrigerant gas leaks during installation ventilate the area immediately Toxic gas may be produced if the refrigerant comes into contact with fire After completing installation check for refrige...

Page 8: ...rosion may shorten the life of the air condi tioner 9 Since drain flows out of the outdoor unit do not place under the unit anything which must be kept away from moisture NOTE Cannot be installed hang...

Page 9: ...on pipe s cut line Wrap the insulation pipe with the finishing tape from bottom to top Caulk pipe hole gap with putty Foot bolt hole centres 580 Foot bolt hole centres 330 250mm from wall Allow space...

Page 10: ...ength and level of the installation ground so that the unit will not cause any operating vibration or noise after installed In accordance with the foundation drawing in fix the unit securely by means...

Page 11: ...oom is 3m Outdoor unit capacity class 2MXS52 2AMX52 3MXS40 3MXS52 3AMX52 3MKS50 4MKS58 Piping to each indoor unit 25m max Total length of piping between all units 50m max If the outdoor unit is positi...

Page 12: ...on oil for R410A Use torque wrenches when tightening the flare nuts to prevent damage to the flare nuts and gas leakage Align the centres of both flares and tighten the flare nuts 3 or 4 turns by hand...

Page 13: ...alve Hi High pressure valve subsequently requires no operation 3 Apply vacuum pumping Check that the compound pressure gauge reads 0 1MPa 76cmHg Evacuation for at least 1 hour is recommended 4 Close g...

Page 14: ...nt may slowly leak out do not leave the flare nut removed for a long period of time Outdoor capacity class 2MXS52 2AMX52 3MXS40 3MXS52 3AMX52 Total length of piping for all rooms 30m Filling a cylinde...

Page 15: ...units Never use piping which has been used for previous installations Only use parts which are delivered with the unit Do never install a drier to this R410A unit in order to guarantee its lifetime Th...

Page 16: ...utdoor unit where the flare nut comes in Use an appropriate wrench to avoid damaging the connection thread by overtightening the flare nut Flare nut tightening torque Flare nut for 9 5 32 7 39 9N m 33...

Page 17: ...wrench 4 After two to three minutes close the gas stop valve and stop forced cooling operation 1 Forced operation 1 Turn the Operation Mode switch SW2 to COOL Heat pump only 2 Press the Forced Operati...

Page 18: ...rews The screws are packed with the terminal board 3 Pull the wire and make sure that it does not disconnect Then fix the wire in place with a wire stop Earth This air conditioner must be earthed For...

Page 19: ...do not operate and enter standby mode according to the operation mode of the set indoor unit 1 2 Priority during high power operation If the indoor unit which is set for priority room setting is oper...

Page 20: ...switch Once the settings are complete reset the power NOTE Install the removed jumper switch as described below This switch will be needed to later disable this setting COOL HEAT Mode Lock S15 only he...

Page 21: ...are not displayed and for three rooms LED 4 is not displayed 2 If the outside air temperature is 5 C or less the wiring error check function will not operate 3 After wiring error check operation is c...

Page 22: ...mperature adjustment Even when the air conditioner is not operating it consumes some electric power If the customer is not going to use the unit soon after it is installed turn off the breaker to avoi...

Page 23: ...1210 HT 3P164392 4P M11B057B Two dimensional bar code is a code for manufacturing 00_CV_3P164392 4P fm Page 2 Tuesday October 30 2012 11 06 AM...

Reviews: