Removal of Electrical Box (Pattern 2)
Si121175
8
Removal Procedure
2
Disconnect the
connector for the four
way valve coil [S80].
When reassembling, insert
the clamp into the hole as
below.
3
Disconnect the
connectors for the
thermistors [S90] [S92]
[S93] and the overload
protector [S40].
[S40]: overload protector
[S90]: thermistors
(outdoor temperature,
outdoor heat exchanger,
discharge pipe)
[S92]: gas pipe thermistors
[S93]: liquid pipe thermistors
Pull out the clamp.
When reassembling, insert
each clamp of the
thermistors into one of the
holes as below.
When reassembling, insert
each clamp into the holes.
When reassembling, the
thermistor harness should
be placed between the
electrical box and the reactor
harness as below.
Step
Procedure
Points
(R17398)
[S80]
Clamp
(R17397)
[S40]
[S90] [S92] [S93]
(R17399)
[S92]
[S93]
(R17401)
Reactor
harness
Thermistor
ASSY
(R17093)
Reactor harness
Thermistor
ASSY