Trial Operation and Testing

• Before starting the test run, measure the voltage at the primary side of the safety breaker. 
• Check that all liquid and gas stop valves are fully open.
• Check that piping and wiring all match. 

1.

Trial operation and testing

1) To test cooling, set for the lowest temperature. To test heating, set for the highest temperature. (Depending on the room 

temperature, only heating or cooling (but not both) may be possible.)

2) After the unit is stopped, it will not start again (heating or cooling) for approximately 3 minutes.
3) During the test run, first check the operation of each unit individually. Then also check the simultaneous operation of 

all indoor units.
Check both heating and cooling operation.

4) After running the unit for approximately 20 minutes, measure the temperatures at the indoor unit inlet and outlet. If the 

measurements are above the values shown in the table below, then they are normal.

(When running in one room)

5) During cooling operation, frost may form on the gas stop valve or other parts. This is normal.
6) Operate the indoor units in accordance with the included operation manual. Check that they operate normally.

2.

Items to check 

ATTENTION

• Have the customer actually operate the unit while looking at the manual included with the indoor unit. Instruct the customer 

how to operate the unit correctly (particularly cleaning of the air filters, operation procedures, and temperature adjustment).

• Even when the air conditioner is not operating, it consumes some electric power. If the customer is not going to use the unit 

soon after it is installed, turn off the breaker to avoid wasting electricity.

• If additional refrigerant has been charged because of long piping, list the amount added on the nameplate on the reverse side 

of the stop valve cover.

Cooling

Heating

Temperature difference 
between inlet and outlet

Approx. 8

°

C

Approx. 15

°

C

Check item

Consequences of trouble

Check

Are the indoor units installed securely?

Falling, vibration, noise

Has an inspection been made to check for gas leakage?

No cooling, no heating

Has complete thermal insulation been done (gas pipes, liquid 
pipes, indoor portions of the drain hose extension)?

Water leakage

Is the drainage secure?

Water leakage

Are the ground wire connections secure?

Danger in the event of a ground fault

Are the electric wires connected correctly?

No cooling, no heating

Is the wiring in accordance with the specifications?

Operation failure, burning

Are the inlets/outlets of the indoor and outdoor units free of any 
obstructions?

No cooling, no heating

Are the stop valves open?

No cooling, no heating

Do the marks match (room A, room B) on the wiring and piping 
for each indoor unit?

No cooling, no heating

01_EN_3P210724-1F.fm  Page 14  Tuesday, October 30, 2012  10:39 AM

Summary of Contents for 2AMX40F2V1B

Page 1: ...nglish Türkçe Installation manual R410A Split series Montaj kýlavuzlarý R410A Split serisi Installationsanleitung Split Baureihe R410A Manuel d installation Série split R410A Montagehandleiding R410A Split systeem Manual de instalación Serie Split R410A Manuale d installazione Serie Multiambienti R410A Εγχειρßδιο εγκατÜστασηò διαιροýìενηò σειρÜò R410A Manual de Instalação Série split R410A Рóêовод...

Page 2: ...0F2V1B 2MXS40G2V1B 2MXS50G2V1B 2MKS40G2V1B 2MKS50G2V1B 2MXS40H2V1B 2MXS50H2V1B 2MKS40H2V1B 2MKS50H2V1B DAIKIN INDUSTRIES LTD Noboru Murata Manager Quality Control Department 1st of Nov 2008 Low Voltage 2006 95 EC Electromagnetic Compatibility 2004 108 EC DAIKIN TCF 015 M1 07 2008 KEMA Quality B V 74736 KRQ EMC97 4957 3SB64417 5A fm Page 1 Tuesday October 7 2008 9 42 AM ...

Page 3: ...5 P6 07 2012 DEKRA Certification B V NB0344 74736 KRQ EMC97 4957 3SB65451 10D Shinri Sada Manager Quality Control Department 2MXS40H3V1B 2MXS50H3V1B 2AMX40G3V1B 2AMX50G3V1B Machinery 2006 42 EC Electromagnetic Compatibility 2004 108 EC Low Voltage 2006 95 EC 3SB65451 10D fm Page 1 Wednesday September 19 2012 10 30 AM ...

Page 4: ...3SB65451 4 fm Page 2 Thursday October 27 2011 4 49 PM ...

Page 5: ...trol box lid may result in electric shocks fire or over heating terminals If refrigerant gas leaks during installation ventilate the area immediately Toxic gas may be produced if the refrigerant comes into contact with fire After completing installation check for refrigerant gas leakage Toxic gas may be produced if the refrigerant gas leaks into the room and comes into contact with a source of fir...

Page 6: ...y shorten the life of the air condi tioner 9 Since drain flows out of the outdoor unit do not place under the unit anything which must be kept away from moisture NOTE Cannot be installed hanging from ceiling or stacked CAUTION When operating the air conditioner in a low outdoor ambient temper ature be sure to follow the instructions described below To prevent exposure to wind install the outdoor u...

Page 7: ...ing Level mounting base optional parts Clamping material Insulation tube Service lid Tape Also insulate the connection on the outdoor unit Use tape or insulating material on all connections to prevent air from getting in between the copper piping and the insulation tube Be sure to do this if the outdoor unit is installed above Cut thermal insulation pipe to an appropriate length and wrap it with t...

Page 8: ...arket It is best to screw in the foundation bolts until their ends are 20mm from the foundation surface When using the reducer packing shown above be careful not to overtighten the nut or the smaller pipe may be damaged about 2 3 1 the normal torque Apply a coat of refrigeration oil to the threaded connection port of the outdoor unit where the flare nut comes in Use an appropriate wrench to avoid ...

Page 9: ...ossible Shortest allow able length per room is 3m Piping to each indoor unit 20m max Total length of piping between all units 30m max If the outdoor unit is positioned higher than the indoor units If the outdoor unit is positioned otherwise If lower than one or more indoor units More than 50 More than 100 Side view Direction of air 1200 or less Wall facing one side Top view More than 50 More than ...

Page 10: ...efrigeration oil for R410A Use torque wrenches when tightening the flare nuts to prevent damage to the flare nuts and gas leakage Align the centres of both flares and tighten the flare nuts 3 or 4 turns by hand Then tighten them fully with the torque wrenches Drain water hole Bottom frame Drain plug Hose available commercially inner dia 16mm Do not apply refrigeration oil to the outer surface Flar...

Page 11: ...anifold and stop the vacuum pump Leave as is for 4 5 minutes and make sure the coupling meter needle does not go back If it does go back this may indicate the presence of moisture or leaking from connecting parts After inspecting all the connection and loosening then retightening the nuts repeat steps 2 3 4 5 Remove the valve caps on the liquid and gas stop valves at the pipes for rooms A and B 6 ...

Page 12: ...ut do not leave the flare nut removed for a long period of time Do not overfill with refrigerant This will break the compressor Filling a cylinder with an attached siphon Stand the cylinder upright when filling There is a siphon pipe inside so the cylinder need not be upside down to fill with liquid Filling other cylinders Turn the cylinder upside down when filling 3 5 6 2 1 4 Please fill in with ...

Page 13: ...il from getting into the system as this would reduce the lifetime of the units Never use piping which has been used for previous installations Only use parts which are delivered with the unit Do never install a drier to this R410A unit in order to guarantee its lifetime The drying material may dissolve and damage the system Incomplete flaring may cause refrigerant gas leakage Gas pipe Liquid pipe ...

Page 14: ...l start 2 Forced cooling operation will end after around 15 minutes and the unit will stop automatically Press the start stop button on the indoor unit to force the operation to stop 3 Use this method to force cooling operation when the outside temperature is 10 C or lower 1 2 Using the wireless remote controller 1 Select cooling operation and press the start stop button The unit will start 2 Pres...

Page 15: ...terminal for connection to the power supply terminal block Place the round crimp style terminals on the wires up to the covered part and secure in place 3 Pull the wire and make sure that it does not disconnect Then fix the wire in place with a wire retainer Room A Room A Room B Outdoor unit Indoor unit Be sure to use the dedicated circuits Safety breaker Earth leakage circuit breaker 50Hz 220 240...

Page 16: ...ot to bend the electric box hook 4 Remove the lower electric box cover 5 Cut the jumper J4 of the PCB inside 6 Go back through step 4 3 2 1 Make sure all components are well secured when doing this CAUTION When removing the upper electric box cover be careful not to bend the hook When returning the lower electric box cover return the notch to the stop valve side When returning the upper electric b...

Page 17: ...move the lower electric box cover 5 Cut the jumper J3 of the PCB inside 6 Go back through step 4 3 2 1 Make sure all components are well secured when doing this CAUTION When removing the upper electric box cover be careful not to bend the hook When returning the lower electric box cover return the notch to the stop valve side When returning the upper electric box cover be careful not to pinch the ...

Page 18: ... indoor unit Instruct the customer how to operate the unit correctly particularly cleaning of the air filters operation procedures and temperature adjustment Even when the air conditioner is not operating it consumes some electric power If the customer is not going to use the unit soon after it is installed turn off the breaker to avoid wasting electricity If additional refrigerant has been charge...

Page 19: ... 1210 HT 3P210724 1F M07B062F Two dimensional bar code is a code for manufacturing 00_CV_3P210724 1F fm Page 2 Tuesday October 30 2012 10 36 AM ...