VENTILATOR MOUNTING
1. Prepare a round through hole in the outer wall. The hole size is shown in the figure below. While preparing the holes consider the method of laying the
power cable.
Ø170
min 500
min 500
min 500
A
Ø170
A
-
A
A
Inner side of the wall
Outer side of the wall
While preparing the hole provide a recess for the cable layout to enable connection of several ventilators in series.
2. Install the telescopic air duct inside the wall, centre the air duct using the mounting plate and seal it with mounting foam.
35
A
Inner side of
the wall
Outer side of
the wall
Seal the centred
air duct using the
mounting foam
3. Install the mounting plate using the dowels (included in the delivery set).
Lean the mounting box
against the wall and mark
four holes for dowels
Lean the mounting box
with screws
Drill the holes and insert the
dowels