background image

TrinityHighway.com

  

15 

Created November 2021 

 

Assembly on a Curve 

Horizontal Curve 

Complete the following steps to place the posts or post foundations along a curve. 

1.  When the cable is placed on a curve, post spacing may need to be reduced based 

on the radius. 

2.  Weak soil conditions may necessitate a larger/deeper footing for the line posts, 

based on the radius of the curve. 

3.  When placing posts on a curve, use the table below to adjust the spacing as required: 

 

Curve Radius 

Post Spacing 

0 to 650’ 

CASS

®

 S4(29) is not recommended. 

650’ to 1300’ [198 m to 396 m] 

10’-6” [3.20 m] post spacing or less (as specified by the state/specifying 
agency) 

Greater than 1301’ [396 m] 

32’-6” [9.91 m] post spacing or less (as specified by the state/specifying 
agency) 

Note: 

If  any  of  the  post  spacing  for  a  particular  radii  grouping  is  larger  than  the  contract 

specifications, use the contract specification post spacing.   

Vertical Curve 

For a sag vertical curve, the recommended minimum K value is 100’ [30 m].

  There is no K value 

limit for crest vertical curves.  

K= L / (g

1

-g

2

L = length of vertical curve in feet [meters) between the two tangents 

g

1

 = grade of tangent in 

g

2

 = grade of tangent out 

When the minimum sag vertical curve value is not met, the use of intermediate terminals at the 
low  point  of  the  sag  curve  is  recommended  to  minimize  the  cables  from  rising  beyond  the 
allowable height tolerance relative to grade.  

 

 

Line Post Foundation Placement 

 

Warning:

    If  the  post  cannot  be  placed,  pursuant  to  these  assembly 

instructions,  because  of  soil  conditions,  or  any  other  environmental  factor, 
please contact the state/specifying agency immediately!  NEVER attempt to 
place posts if these assembly instructions cannot be complied with. 

Post Alignment 

Lay  out  the  post  alignment  and  post  spacing  according  to  the  contract  specifications. 
CASS

®

 S4(29) maximum post spacing is 32’-6” [9.9 m]. 

 

Driven Foundation Sleeve With and Without Soil Plate 

Complete the following steps for a driven foundation sleeve assembly. 

1.  Drive  the  foundation  sleeve  (PN-33975G)  or  foundation  sleeve  with  soil  plate  (PN-

33976A)  with  an  appropriate  driving  head.  During  the  driving  process  ensure  that  the 
sleeve is aligned, properly oriented (with interior tabs 15” [375 mm] from the top of the 
tube  sleeve  and  the  3”  [75  mm]  side  parallel  to  the  roadway),  soil  is  prevented  from 
coming up into the sleeve, and the sleeve is not damaged.      

Summary of Contents for TRINITI HIGHWAY CASS S4

Page 1: ......

Page 2: ...CASS S4 29 could result in serious injury or death Important These instructions are for standard assembly specified by the state specifying agency In the event the specified system assembly maintenanc...

Page 3: ...nce Records 34 CASS S4 29 Temperature Tension Chart 35 Tension Log Cable Safety System 36 Appendix A Flare Assemblies 30 1 Flare 37 Appendix B Cable Barrier Overlap 38 Appendix C Encountering Rock 39...

Page 4: ...ASS S4 29 assemblies specified by the state specifying agency If you need additional information or have questions about CASS S4 29 please contact the state specifying agency that has planned and spec...

Page 5: ...uated and restored to its original specified condition or replaced as the state specifying agency determines requires as soon as possible Product selection approval proper installation and maintenance...

Page 6: ...own geotechnical engineer Warning Be aware of hazards of using compressed air small objects may become projectiles Failure to follow this warning can result in serious injury or death to the workers a...

Page 7: ...astic spacers keep the cables positioned at approximately 4 100 mm on center from each other A stainless steel strap is placed around the post below the top cable The post spacing will be in accordanc...

Page 8: ...4 5 16 Hex Nut A563 5 8 Flat Washer F844 PN 3310G PN 3361G PN 3536G 5 8 Lock Washer 5 8 Hex Nut 1 Stud Flattened RHT PN 3537G PN 3700G PN 3701G 1 Stud Flattened LHT 3 4 Flat Washer 3 4 Flat Washer F43...

Page 9: ...3 x 7 PN 4211G PN 4779G PN 4902G 5 16 x 1 3 4 Hex Bolt A307 3 4 x 4 1 2 Hex Bolt A325 1 Flat Washer F436 PN 4903G PN 4959G PN 5225G 1 Hex Nut A194 2H 3 4 Heavy Square Nut 5 8 X 7 1 2 HAS SUPER Rod Chi...

Page 10: ...Reflector Spacer Yellow PN 5702B PN 5707T PN 5708B 4 Cable Reflector Spacer White Stainless Steel Post Strap Sleeve Cover CASS Post PN 5709B PN 5711G PN 5724B CASS Thermometer Infrared 3 4 Turnbuckle...

Page 11: ...r Roadside RIGHT CASS Tension Meter 1 Cable Field Splice Left PN 5910G PN 5919B PN 6722G 1 Cable Field Splice Right 4 x 2 8 Rebar Rod 5 8 X 8 ATR CHSL PT A449 PN 9021G PN 33903A PN 33908G Bearing Angl...

Page 12: ...ng Cage PN 33934A PN 33935A PN 33936A Bottom CRP in Concrete Top CRP Bottom CRP w Soil Plate PN 33952A PN 33953G PN 33956G Driven Terminal Sleeve w Soil Plates S3 Posts 4 9 CASS TL 3 Post in Sleeve CA...

Page 13: ...ttened LHT 3 4 Stud Flattened RHT Important Trinity Highway makes no recommendation whether use or reuse of any part of the system is appropriate or acceptable following an impact It is the sole respo...

Page 14: ...878B CASS Thermometer Infrared PN 5709B Abrasive Cutoff Blade Saw C Clamps CASS Cable Pulling Tool PN 5850B Locking Pliers Duct tape Pry Bars Line String Plumb Line Straight Edge Level Drift Pin Tape...

Page 15: ...er FHWA and AASHTO guidance for ANY NCHRP Report 350 cable system placed on side slopes steeper than 1V 10H shall not be placed within 1 to 8 0 3m to 2 4m from the ditch line Barrier Alignment Follow...

Page 16: ...ers between the two tangents g1 grade of tangent in g2 grade of tangent out When the minimum sag vertical curve value is not met the use of intermediate terminals at the low point of the sag curve is...

Page 17: ...of posts Sleeve in Mow Strip When a mow strip is used that meets the criteria in drawing SS 730 sleeve PN 33968G may be used Complete the following steps for placing a sleeve in a mow strip Footing u...

Page 18: ...e Complete the following steps for a post in the sleeve assembly 1 Place the post sleeve cover PN 5823B on the bottom end of the CASS S4 29 post PN 33953G 2 Place the post in the sleeve so it rests on...

Page 19: ...drawing requirements A standard spiral rebar cage that may be applicable is PN 33916B See Figure 2 4 Place the rebar cage in the footing hole ensuring a minimum of 3 75 mm of concrete surrounds the ca...

Page 20: ...P does not protrude more than 4 100 mm above the finished grade 3 Backfill the hole with material in 6 150 mm lifts and compact to optimum compaction CCT Line Footings Post Alignment Lay out the post...

Page 21: ...ll be the footing depth minus 4 100 mm The two vertical re bars do not have to be attached to the ring 6 Smooth off the top of the footing 7 Allow the footing to attain the required concrete strength...

Page 22: ...9B on the bottom end of the terminal line posts PN 33910G 2 Place post PN 33910G in sleeves 4 to 9 and post PN 33955G The cover will be located at the top of the sleeve Terminal Line Posts in Driven S...

Page 23: ...cable PN 5819G starts at CRP 3 post location 3 and is placed on the front side traffic side of the line terminal posts B Place the right threaded end of the fitting through the hole formed by the top...

Page 24: ...the reel first The right hand fitting end for the cable must come off first and the end is painted red for identification When there is more than one cable on the reel the last cable placed on the ree...

Page 25: ...e Figure 6a for a 1 Cable Splice PN 5633G and Figure 6b for 3 4 Cable Splice PN 5698G Perform the following steps to complete a splice using a field applied fitting and a turnbuckle 1 Ensure that the...

Page 26: ...rnbuckle Torpedo Cable Splice When two cable ends are spliced together other than where spliced with a turnbuckle a Torpedo Cable Splice can be used The Torpedo Cable Splice PN 4099G assembly is made...

Page 27: ...mplete the following steps for laying out the cables and attaching them to the posts 1 Using the Trinity Highway Shop Drawings for the cable run to select the cables needed to complete the assembly 2...

Page 28: ...he time of tensioning The tension meter shall be set for pre stretched cable An infrared thermometer is to be on site at the point of tensioning to obtain the correct cable temperature If an infrared...

Page 29: ...6 Place a right hand field applied fitting using the procedures in the Field Applied Fittings with a Turnbuckle section 7 On the CCT end place a turnbuckle PN 5826G on the fitting by only a couple of...

Page 30: ...ing an impact It is the sole responsibility of the state specifying agency and its engineers or it agent to make that determination It is critical that you inspect this product after assembly is compl...

Page 31: ...ves The cable can be held down and the traffic or emergency vehicles can pass over it PPE equipment such as protective gloves safety goggles and mask must always be used Keep personnel out of the area...

Page 32: ...cut If the tension cannot be obtained at the turnbuckles at each side of the splice it may be necessary to follow the procedures in the Tension and Tension Meter Section Some assemblies may have field...

Page 33: ...ction After completing one 1 of the four 4 methods above check the tension on the cable with the tension meter and adjust the turnbuckles to bring the cable to the correct tension based on the cable t...

Page 34: ...19 7 Ensure the top of the Bottom CRP s does not protrude more than 4 100 mm above the finished grade p 18 8 Ensure the bent part of the Cable Anchor Bracket at the CRP s is up and hooked over the Top...

Page 35: ...minimum consistof Visual Drive By Inspections Recommended Frequency Monthly Check for damage caused by vehicle impacts Check for damage caused by impacts from snowplow mowing or roadway operations Che...

Page 36: ...4 24 9 45 5500 7 24 4 50 5300 10 23 6 55 5100 13 22 7 60 5000 16 22 2 65 4800 18 21 4 70 4600 21 20 5 75 4500 24 20 0 80 4300 27 19 1 85 4100 29 18 2 90 4000 32 17 8 95 3800 35 16 9 100 3600 38 16 0...

Page 37: ...le ______________ Bottom __________ Bottom __________ Bottom ______________ _________________________________________________________________________________________________________ Loc ___Actual Lbf...

Page 38: ...TrinityHighway com 37 Created November 2021 Appendix A Flare Assemblies 30 1 Flare...

Page 39: ...TrinityHighway com 38 Created November 2021 Appendix B Cable Barrier Overlap...

Page 40: ...the foundation tube so the top of the tube will be flush with finished ground C Follow the steps in C and D in Option A above Foundation Tubes with Soil Plates For Foundation with Tubes with Soil Plat...

Page 41: ...hesive manufacturer s recommendations 3 Place the rods and adhesive in the holes according to the manufacturer s recommendations Note A 5 8 16 mm mechanical anchor with a pull out strength of 10 000 l...

Page 42: ......

Reviews: