6. Installation
PNEG-240
Chain Feeding System
23
Installing the Trough, Couplers and Corners
Begin by loosening the power shoes and/or chain guides located in the hopper. The sections of trough will
need to be “pinched” under them later in the installation.
Figure 6D
Distribute the sections of trough, couplers and corners to their approximate locations in the circuit. Insert
the first section in the outgoing end of the hopper. Do this by gently squeezing the sides of the trough (D)
and pushing into the hopper. Loosen the power shoe bolts (F). Make sure that the trough is inserted under
the power shoe (E) and against the power shoe bolts (F). Once the trough is in place, tighten the bolts
holding the power shoe (C) in place.
Figure 6E
Ref #
Description
A
Loosen Bolts
Ref #
Description
Ref #
Description
B
Drive Gear
E
Trough Under Power Shoe
C
Power Shoe
F
Power Shoe Bolts
D
Trough