22
Figure 3-10 Wire stripping of DC input
(c) Crimp the terminal as shown in Figure 3-11:
Figure 3-11 Terminal crimping of DC input
(d) The order of wire connection from left to right is PV1-, PV1+, PV2-,
PV2+. Connect the PV1- and PV2- to the corresponding fuse socket of the
negative pole and connect the PV1+ and PV2+ to the corresponding fuse
socket of the positive pole with M5×12 bolts (4 PCS in total) as shown in
Figure 3-12:
Figure 3-12 Wire connection of DC input
(e) For the inverter with 1 MPPT working alone, connect J1 (IN1+) with J3