Installation 

Mounting 

DA 
DA 

DALI 

Choosing a Suitable Location 

The detector should be sited so that the occupants of the room fall inside the detection pattern shown on page 1, at a 
recommended ceiling height of 2.8m. Note that the lower the sensor is installed the smaller the detection range will be, 
subject to the parameters shown on the detection diagram. 

 

Avoid direct sunlight entering the sensor.  

 

Do not site within 1m of forced air heating or ventilation.   

 

Do not fix to a vibrating surface. 

 

Do not exceed maximum length of cable (200m) on data bus. 

 

Do not exceed maximum bus loading (200mA). 

Wiring diagram 

The EBR-MINPIR-DALI supplied with two 1m wires to 
connect to the DALI network. The device is designed to 
operate correctly with reversed polarity.  

Remove bottom 
of 2 small 
retention arms 

Standalone mounting 

The product is designed to be mounted into a ceiling tile or plasterboard ceiling using the flush holder as shown below. If 
flush mounting in a panel >6mm thick, remove bottom of retention arms with side cutters. 

Luminaire mounting 

The product is also designed to be mounted directly to a luminaire, either on the inside or outside. 

 

The PIR lens must have a view outside the luminaire. 

 

For optimum lux measurement,  the lens must be shielded as much as possible from the light source. 

 

If flush mounting in a panel >6mm thick, remove bottom of retention arms with side cutters. 

Flush mounting 

The product can be mounted using the 
flush mount ring as shown. If flush 
mounting in a material that is greater 
than 6mm thick, remove bottom of 
retention arms with side cutters. A 
32mm diameter hole will be required to 
mount the flush mount ring. 

Ø19.5m

Ø3.5m

19mm 

Use the lugs on rear of detector to 
secure into thin sheet metal (1mm 
max.). 

Surface mounting 

Devices (detectors / input units) and ballast combinations 

for 200mA supply. 

This 

assumes that the sensor LEDs are all on, and the 

sensor is receiving IR communication.

 

 

devices 

and up to 64 ballasts 

 

5 devices and up to 55 ballasts 

 

6 devices and up to 44 ballasts 

 

7 devices and up to 33 ballasts 

 

8 devices and up to 22 ballasts 

 

9 devices and up to 12 ballasts 

 

10 devices and up to 2 ballasts 

 

In most realistic scenarios, only one LED is on at a time 

and only one detector is receiving IR; guidance changes 

to. 

 

10 devices up to 64 ballasts 

 

11 devices up to 60 ballasts 

 

12 devices up to 55 ballasts 

 

13 devices up to 50 ballasts 

 

14 devices up to 48 ballasts 

 

15 devices up to 44 ballasts 

Addressing limits of DG64 

 

5 input units of 7 channels each 

 

10 detectors 

DALI bus loading 