Cooper Power Systems VXE Control Installation And Operation Instructions Manual Download Page 16

Manual Closing Procedure

The manual closing tool (shown in Figure 11) permits
manual closing of the main contacts of the VXE recloser
for test purposes, when a high-voltage source for closing
is not available. Minimum-trip current and operating
sequence can be tested in this manner. Refer to instruc-
tions covering 

Manual Operation Of De-energized

Recloser

for closing procedure when using the manual

closing tool. The best procedure is to have one person
operate the closing tool while another regulates the trip-
ping circuit and observes test results.

Manual Operation of a De-energized
Recloser

The manual closing tool is only to be used for closing a
de-energized recloser.

The de-energized recloser is manually closed by raising
the yellow manual operating handle to the Closed posi-
tion and using the manual closing tool to rotate the main
operating shaft of the recloser mechanism 90 degrees.
Rotation of the main operating shaft must be completed
before the undervoltage lockout feature operates. Refer
to the 

Undervoltage Lockout

section of this manual.

Use the following procedure for manual closing of a de-
energized recloser:

1.

Remove the pipe plug from the side of the recloser
head casting and insert the manual closing tool to
engage the main operating shaft.

2.

Raise the yellow operating handle to the CLOSED
position.

3.

Rotate the closing tool about 1/4 turn clockwise, to
close the recloser contacts. Avoid forcing the closing
tool beyond the mechanism stop: doing so may shear
the pin on the main operating shaft.

4.

A de-energized recloser can be tripped open by
pulling the yellow manual operating handle down to
the LOCKOUT position.

5.

Be sure to replace the pipe plug in the head casting
before placing the recloser in service.

High-Potential Insulation Level
Withstand Tests

High-potential withstand tests provide information on the
dielectric condition of the recloser. Testing is performed at
75% of the rated low-frequency withstand voltage.

Always use a suitable test cage and follow procedures
outlined in the 

Testing: Safety Requirements

section of

this manual.

• For a VXE15 recloser, test at 37.5 kV rms.

• For a VXE27 recloser, test at 45.0 kV rms.

Closed-Contacts High-Potential Test

1.

Manually close the recloser contacts.

2.

Ground the recloser head casting and control.

3.

Apply the proper test voltage to the source-side
bushing.

4.

The recloser should withstand the test voltage for 60
seconds.

Type VXE Single-Phase Electronically Controlled Recloser Installation and Operation Instructions

16

Figure 11.
The manual closing tool is used to close a de-ener-
gized Type VXE recloser.

921124KM

WARNING: 

Hazardous voltage. Never use a

manual closing tool to close an energized reclos-

er. Manually closing an energized recloser will result in
failure of the vacuum interrupter and can result in con-
tact with high voltage, which can cause death or severe
personal injury.

T236.0

!

IMPORTANT:  

After each recloser trip, while the

closing solenoid plunger is moving downward, two
metallic clicks will be heard. The first click is the main
toggle latch resetting. The second click is the closing
solenoid contactor closing. As soon as these clicks are
heard, the closing tool can be turned to close the
recloser.

CAUTION: 

Radiation. At voltages up to the

specified test voltages, the radiation emitted by

the vacuum interrupter is negligible. However, above
these voltages, radiation injurious to personnel can be
emitted. See 

Service Information S280-90-1

Vacuum

Interrupter Withstand Test Voltage Ratings Information

,

for further information.

G109.2

!

Summary of Contents for VXE Control

Page 1: ...rogramming and Operation 7 Type VXE Electronic Control 7 Programming the Control Settings 8 Specifications and Ratings 10 Dimensions 11 Installation Procedure 12 Placing the Recloser In Service 13 Ope...

Page 2: ...ting main taining or testing this equipment carefully read and understand the contents of this manual Improper operation handling or maintenance can result in death severe personal injury and equipmen...

Page 3: ...ss is discov ered file a claim with the carrier immediately Check for oil leakage and tighten all bolts that may have loosened during shipment especially the tank mounting bolts Tank mounting bolts sh...

Page 4: ...voltage closing is sup plied through a 2 pin connector mounted on the recloser head Closing Solenoid Operation The closing operation is illustrated by considering the recloser to be connected to the l...

Page 5: ...ion the lever is pulled from under the sleet hood to its down position as shown in Figure 2 The lever must be manually returned to the up position in order to return the recloser to its pre programmed...

Page 6: ...eration section of this manual for further information The VXE control can be equipped with an optional SCADA input output board to provide remote operation and status functions for SCADA applications...

Page 7: ...pening actuator In addition a control battery is required to supply power to the control during the reclose intevals If line current drops below 3 A or the recloser is in the open position power is th...

Page 8: ...le protecting fuses from tem porary faults Sequence Coordination is always active for the number of TCC1 operations selected for the VXE control For example for two trip operations on TCC1 and two tri...

Page 9: ...TCC2 Time Current Curve Modifiers The DIP switches labeled S6 Figure 5 are used to mod ify the shape of the time current curve produced by the TCC plug in card for TCC1 and or TCC2 Each TCC plug in ca...

Page 10: ...imate inches 0 4 0 5 Contact Close Time Close Signal To Contact Make seconds 0 19 0 24 Open Contact Travel Time Open Signal To Contact Part seconds 0 014 0 022 Interrupting Time Open Signal to Arc Ext...

Page 11: ...Pole Bolt Connector NO 6 350 MCM 16 UNC 2B 8 5 Figure 6 Dimensions of Types VXE15 and VXE27 reclosers Type Bushing Type A B C VXE15 standard 1156 45 5 483 19 270 10 5 VXE15 extra creepage 1237 48 75 5...

Page 12: ...ug as shown in Figure 4 Make sure that all DIP switch settings are set correctly and that the control cable is connected between the recloser and control 6 Mount the recloser Use the lifting lug locat...

Page 13: ...en placing the recloser in service Be sure that the control battery is properly connected When the recloser is connected and source side high voltage lines are energized by closing the source side dis...

Page 14: ...dle down and returning the yellow handle to its up Closed position If the VXE con trol is equipped with the optional SCADA input output accessory board the recloser can be remotely closed from lockout...

Page 15: ...n the 600 5 tap 3 Ammeter Must have a rating based on the level of test current Since the control is responsive to peak current it is recommended that metering responsive to peak current be used when...

Page 16: ...the pipe plug in the head casting before placing the recloser in service High Potential Insulation Level Withstand Tests High potential withstand tests provide information on the dielectric condition...

Page 17: ...when the recloser trips and compare to the VXE control s pro grammed minimum trip value Sequence of Operation Test The operating sequence can be checked by using the manual closing tool to close the r...

Page 18: ...ating correct operation of the clos ing solenoid Type VXE Single Phase Electronically Controlled Recloser Installation and Operation Instructions 18 Figure 13 Suggested test diagram for high voltage c...

Page 19: ...SCADA I O board also includes dry contacts to provide remote status information All remote features are accessed through a 19 pin recep tacle Type MS 22 14 female mounted on the bottom of the control...

Page 20: ...Department offers recloser mainte nance training classes These classes taught by experi enced service technicians are held at the factory s in house training facility For additional information contac...

Reviews: