DC Inverter Multi VRF System User Manual
18
②
Specification of power cord is based on the working condition where ambient temperature is
40
℃
and multi-core copper cable (working temperature is 90
℃
, e.g. power cable with YJV cross-
linked copper, insulated PE and PVC sheath) is lying on the surface of slot. If working condition
changes, please adjust the specification according to national standard.
③
Specification of circuit breaker is based on the working condition where ambient temperature
of circuit breaker is 40
℃
. If working condition changes, please adjust the specification according to
national standard.
5 Check Items after Installation and Test Operation
5.1 Check Items after Installation
Check items
Possible conditions due to improper installation
Check
Each part of the unit is installed securely?
Unit may drop, shake or emit noise.
Gas leakage test is taken or not?
Insufficient cooling (heating) capacity
Unit gets proper thermal insulation or not?
There may be condensation and dripping.
Drainage is smooth or not?
There may be condensation and dripping.
Is the voltage in accordance with the rated
voltage specified on the nameplate?
Unit may have malfunction or components may get
damaged.
Is the electric wiring and pipe connection
installed correctly?
Unit may have malfunction or components may get
damaged.
Unit is securely grounded or not?
Electrical leakage
Power cord meets the required specification?
Unit may have malfunction or components may get
damaged.
Is the air inlet/outlet blocked?
Insufficient cooling (heating) capacity
Length of refrigerant pipe and the charging
amount of refrigerant are recorded or not?
The refrigerant charging amount is not accurate.
Binding pieces on compressor feet are
removed or not?
Compressor may get damaged.
5.2 Test operation and debugging
Notice:
①
After finishing the first installation or replacing the main board of outdoor unit, it is necessary
to perform test operation and debugging. Otherwise, unit won’t be able to work.
②
Test operation and debugging must be performed by professional technicians or under the
guidance of professional technicians.
5.2.1 Prepare the test operation and debugging
1)
Do not connect power until all installation work is finished.
2) All control circuits and wires are correctly and securely connected.
3)
Check whether the fixing loops for compressor foots are removed.
4) All small pieces, especially metal chips, thread ends and forceps holder, must be removed
from the unit.
5) Check whether unit’s appearance and pipeline system has been damaged during
transportation.
6) Calculate the quantity of refrigerant that needs to be added according to the pipe length.
Pre-charge the refrigerant. In case that the required charging quantity is not reached while
refrigerant can’t be added, record the quantity of refrigerant that still needs to add and
complement the quantity during test operation. For details of adding refrigerant during test
operation, see below.