8
CONTRACOR
®
Version 1.5
4. Abrasive blasting operations.
4.1. Start up.
1.
Check all connections from compressor to the nozzle to ensure that they are properly
fixed (badly fixed air hose of the compressor cause a serious damage).
2.
Ensure that abrasive blasting machine is filled with abrasive.
3.
Ensure that the necessary safety measures for you and others are observed:
—
protective equipment is used,
—
purified air is fed to the helmet.
4.
Always check position of RC handle lever, which should be in the safety position with
the holder in vertical position
5.
Feed compressed air to the machine intake.
ATTENTION!
MACHINE MAXIMUM OPERATING PRESSURE — 10 bar.
6.
Close both ball valves at the RC valve.
7.
Ensure that there is no leak in the system. Air should come ONLY out of the vent
under the RC handle lever.
Summary of Contents for BlastRazor Z-100RCS
Page 4: ...4 CONTRACOR Version 1 5 2 Package and description Fig 2 1 8 2 13 14 4 5 1 3 6 7 9 11 10 12...
Page 18: ...18 CONTRACOR Version 1 5 2 Ansicht Arbeitsaufbau Abb 2 1 8 2 13 14 4 5 1 3 6 7 9 11 10 12...
Page 30: ...30 CONTRACOR 1 5 1 31 2 32 3 34 4 36 5 38 6 39 7 41 Contracor Contracor...
Page 31: ...31 CONTRACOR BlastRazor Z 100 RCS BlastRazor Z 200 RCS Art 10400102 10400202 1 1 2 3 4 5 6...
Page 32: ...32 CONTRACOR 1 5 2 8 2 13 14 4 5 1 3 6 7 9 11 10 12 2 1...
Page 34: ...34 CONTRACOR 1 5 3 3 1 1 2 DMH TWINLINE 3 4 DMH 5 DMH 6 Twinline 1 5 7 8...
Page 36: ...36 CONTRACOR 1 5 4 4 1 1 2 3 4 5 10 6 7...
Page 38: ...38 CONTRACOR 1 5 5 5 1 5 2 1 CAF 3 2 3 5 3 160 1 2 3 5 2...
Page 39: ...39 CONTRACOR BlastRazor Z 100 RCS BlastRazor Z 200 RCS Art 10400102 10400202 6 6 1 1 2 3 4...
Page 40: ...40 CONTRACOR 1 5 Twinline Twinline RCV RCV TWINLINE...