Conductix-Wampfler Festoon Heavy Duty C-Track Manual Download Page 7

Heavy Duty C-Track Manual

         

Located longitudinal center line of runway where channel is to be 
installed.

If the C-Track is to be attached under a beam or stud, the hanger 
locations should be marked and drilled, or crossarm support 
installed.

Track Hanger Installation

9/16” Open / Box End Wrench required.

The track hanger is designed to be mounted on angle iron brackets 
with one mounting hole - can also be mounted on C-Track 
crossarm support or other suitable structures. 

One track hanger is required for each crossarm support bracket for 
each track run at 10ft. spacing (or 5ft. spacing for SST track). Extra 
track hanger and crossarm support bracket is required in storage 
area.

1.  Slip the appropriate number of hangers on each section of 

C-Track. 

2.  Bolt the section loosely in place, joining the ends of the 

channels with splice joints as you progress. See 

Figure 7-1.

3.  Align set screws with holes in C-Track and tighten. See 

Figure 

7-1.

Track Joint Assemblies Installation

7/16” Open / Box End, 1/8” Allen Wrench 3/32” Drill Bit required.

Track joints clamp for secure attachment and proper alignment of 
track section. Each kit includes four set screws and nuts. Welded 
splice assemblies are also available. See 

Figure 7-2.

1.  Install the joints and tighten fasteners using a 1/8” Allen and a 

7/16” open/box end or weld in place. See 

Figure 7-2.

2.  If C-Track must be shortened, the hole pattern must be 

transferred to the new cut length. See 

Figure 7-3.

SECTION 3 - INSTALLATION

Figure 7-1

Figure 7-2

Figure 7-3

1.  Hole Pattern

1

Summary of Contents for Festoon Heavy Duty C-Track

Page 1: ...Festoon Manual Heavy Duty C Track Heavy Duty C Track Manual XA 966300 3...

Page 2: ...ing goods shall arise once Buyer returns such goods FOB point of original shipment by Seller at the risk and cost of Buyer Goods replaced by Seller shall become the property of Seller There is no guar...

Page 3: ...ger Installation 7 Track Joint Assemblies Installation 7 Anchor Clamp Installation 8 Girder Clamp Installation 8 End Clamp Installation 8 Cable Trolley Installation 9 Tow Trolley Control Box Trolley I...

Page 4: ...FETY Safety Information Responsibility All owner operator and maintenance personnel must read and understand all manuals associated with this product before installation operation or maintenance The m...

Page 5: ...rack Hanger Installation See Section 3 Cable Trolley Installation See Section 3 Cable Installation See Section 3 End Clamp See Section 3 End Stop Installation See Section 3 2 Endstops Needed per Contr...

Page 6: ...ed The loop depth is the distance from the top of the track to bottom of the cable loop Maximum cable stack height is 1 5 Maximum recommended cable height is 65 For round cable the maximum recommended...

Page 7: ...ired in storage area 1 Slip the appropriate number of hangers on each section of C Track 2 Bolt the section loosely in place joining the ends of the channels with splice joints as you progress See Fig...

Page 8: ...s are designed to hold the crossarm supports to the I beam Two girder clamps required per crossarm support 1 Orient square nut flush against inside bottom surface of C Track crossarm support See Figur...

Page 9: ...ontrol festoon system The Control Box Trolley consists of a mobile junction box or a quick disconnect connector to which a push button pendant may be wired 1 Place the Tow Trolley Control Box Trolley...

Page 10: ...better suited to handle this force Note the specified cable loop depth and allowance for hookup 4 Arrange the cable package with a width to height ratio of 3 or 4 to 1 Tall narrow cable stacks can be...

Page 11: ...align tow bar with the Tow Trolley See Figure 11 2 Pre Assembled Festoon System Installation Pre assembled festoon systems are typically built and shipped installed on a C Track Channel by Conductix W...

Page 12: ...the voltage or amperage rating of the cable Overheating fire damages to equipment or personal injury could result Operate the festoon system within the electrical and mechanical limits it was intende...

Page 13: ...Heavy Duty C Track Manual 13...

Page 14: ...ADA 18450 J A Bombardier Mirabel QC J7J 0H5 Customer Support Phone 1 800 667 2487 Phone 1 450 565 9900 Fax 1 450 851 8591 info ca conductix com M XICO Calle Trevi o 983 C Zona Centro Apodaca NL M xico...

Reviews: