7.4.

 

Accuracy at 120V, 60 Hz input, POS peak. 

 

7.4.1.

 

Connect an oscilloscope to the 100:1 BNC connector on the front panel of the CDT. 
 

7.4.2.

 

Connect the L and G front panel test jacks across the RC time constant CAL-BOX, 1s terminals 
“A’ and “B”. 

 

7.4.3.

 

Set the CDT for the following test: 

 

Trigger on POS 

 

Voltage Test 

 

Voltage setting: 50.0 V 

 

Line to Gnd measurement 

 

7.4.4.

 

Perform  three  tests  and  confirm  that  it  disconnects  within  -5%  /+0%  of  the  peak  voltage  as 
specified in section 7.1. 
 

7.4.5.

 

Circle PASS on section 5 of CAL-Log-001-CDT 240 if the verification was successful. 

7.4.5.1.

 

Expected Value: Value of previous Positive Sine Wave Peak. 

7.4.5.2.

 

Tolerance: Expected Value -5%/+0% of reading. 

7.5.

 

Accuracy at 120V, 60Hz input, NEG peak. 

 

7.5.1.

 

Connect a scope to the BNC connector on the front panel of the CDT. 
 

7.5.2.

 

Connect the L and G front panel test jacks across the RC time constant CAL-BOX, 1s terminals 
“A’ and “B”. 
 

7.5.3.

 

Set the CDT for the following test: 

 

Trigger on NEG 

 

Voltage Test 

 

Voltage setting: 50.0 V 

 

Line to Gnd measurement 

 

7.5.4.

 

Perform three tests and confirm that it disconnects within -5%/+0% of peak voltage as specified in 
section 7.1. 
 

7.5.5.

 

Circle PASS on section 5 of CAL-Log-001-CDT 240 if the verification was successful. 

7.5.5.1.

 

Expected Value: Value of previous positive Sine Wave Peak, as it shown it in 

Figure 8

. 

7.5.5.2.

 

Tolerance: Expected Value -5% /+0% of reading. 

 

Summary of Contents for CDT-240

Page 1: ...IALS EQUIPMENT NEEDED 5 1 Calibrated DMM Qty 2 DMM1 for voltage RMS below 50V and the DMM2 for voltages RMS 50V or greater 5 2 Calibrated Oscilloscope with 10x or 100x probe 5 3 DC power supply 60V 5...

Page 2: ...document instead of mentioned CAL Log 2 2 Plug in the CDT 240 power cord plug in the EUT power cord to the proper value 90 260V 50 60Hz disconnect all the test leads attached to G L or N outputs disco...

Page 3: ...so that the CDT is not armed The oscilloscope should measure 0V on the BNC connector we expect to get same as Figure 2 adjust P3 in order to set this value Figure 2 Zero output on BNC connector with C...

Page 4: ...be 0 0V because the voltage decayed to zero in 3s Adjust P4 as needed so that the measured voltage is 0 0V turning the potentiometer clockwise makes the reading lower i e more negative Repeat the tes...

Page 5: ...50 0 V Line to Gnd measurement 5 1 3 Press the test button once to ARM the CDT You should see a sine wave signal on the oscilloscope as it shows it in Figure 5 Figure 5 Sine Wave Output on CDT 240 BNC...

Page 6: ...f the voltage is 60VDC for example You can see both TP7 TP6 test points on Figure 6 5 2 3 Record the Neutral to Ground voltage on section 3 N G of CAL Log 001 CDT 240 5 2 3 1 EUT Test Voltage DMM2 Neu...

Page 7: ...EUT voltage is 120V for example To read both meters simultaneously press the HOLD button on both meters at the same time if available 6 1 5 Record both input voltage and L G BNC voltage on section 4 o...

Page 8: ...EUT Test Voltage Expected value 6 2 4 3 Tolerance Expected Value 1 of reading 6 3 Line to Neutral No adjustment verification only 6 3 1 If the EUT connection is reverse connect as normal Figure 7 6 3...

Page 9: ...84 ms for 60 Hz 1 01 ms for 50 Hz 7 2 All measurements are positive peak disconnect POS unless otherwise specified An example of a very accurate disconnect is shown below in Figure 8 Figure 8 Example...

Page 10: ...tion was successful 7 4 5 1 Expected Value Value of previous Positive Sine Wave Peak 7 4 5 2 Tolerance Expected Value 5 0 of reading 7 5 Accuracy at 120V 60Hz input NEG peak 7 5 1 Connect a scope to t...

Page 11: ...he test time result on the CDT 240 8 2 Neutral to Ground Voltage Accuracy 8 2 1 Edit the test parameters for a Voltage test Trigger on NEG Voltage Test Voltage setting 50 0 V Neutral to Ground measure...

Page 12: ...uracy 9 2 1 Edit the test parameters for a Delay test Trigger on POS Delay Test Delay setting 1 second Line to Neutral measurement 9 2 2 Connect L N to 1s time constant terminals A and B of CAL BOX an...

Page 13: ...onfirm the oscilloscope voltage waveform after 1 second of Main relay disconnection measurement corresponds to the CDT 240 within 2 of reading 0 8V 9 3 7 Record on section 7 of CAL Log 001 CDT 240 9 3...

Reviews: